Skip to content
cccskills
FreePublished on GitHub

schedule-compression

Compress construction schedules using crashing and fast-tracking techniques. Analyze cost-time tradeoffs and find optimal acceleration strategies.

The English summary is being prepared. Showing the original description.

See how to install

Files included (3)

  • SKILL.md16.6 KB
  • claw.json529 B
  • instructions.md1.2 KB

SKILL.md (original)

Review the instructions the agent will receive before you install.

Schedule Compression

Overview

Compress construction schedules when project deadlines are at risk. Apply crashing (adding resources) and fast-tracking (parallel activities) to accelerate delivery while managing cost and risk.

"Strategic compression can recover 20% of schedule with 10% cost increase" — DDC Community

Compression Techniques

┌─────────────────────────────────────────────────────────────────┐
│                  SCHEDULE COMPRESSION                            │
├─────────────────────────────────────────────────────────────────┤
│                                                                  │
│  CRASHING                          FAST-TRACKING                 │
│  ────────                          ─────────────                 │
│  Add resources to reduce           Overlap sequential            │
│  activity duration                 activities                    │
│                                                                  │
│  Before:  ████████ (10d)          Before:  A ──→ B ──→ C        │
│  After:   █████ (5d) + $$$         After:   A ──→ B             │
│                                              └──→ C              │
│  Cost: Higher labor/OT             Risk: Rework if A changes    │
│                                                                  │
└─────────────────────────────────────────────────────────────────┘

Technical Implementation

from dataclasses import dataclass, field
from typing import List, Dict, Optional, Tuple
from enum import Enum

class CompressionMethod(Enum):
    CRASH = "crash"
    FAST_TRACK = "fast_track"
    HYBRID = "hybrid"

@dataclass
class Activity:
    id: str
    name: str
    normal_duration: int
    crash_duration: int  # Minimum possible duration
    normal_cost: float
    crash_cost: float  # Cost at crash duration
    predecessors: List[str] = field(default_factory=list)
    is_critical: bool = False
    current_duration: int = 0

    def __post_init__(self):
        if self.current_duration == 0:
            self.current_duration = self.normal_duration

    @property
    def crash_slope(self) -> float:
        """Cost per day of crashing."""
        duration_diff = self.normal_duration - self.crash_duration
        if duration_diff == 0:
            return float('inf')
        return (self.crash_cost - self.normal_cost) / duration_diff

    @property
    def days_available_to_crash(self) -> int:
        """Days activity can still be crashed."""
        return self.current_duration - self.crash_duration

@dataclass
class FastTrackOption:
    activity1_id: str
    activity2_id: str
    overlap_days: int
    risk_level: str  # low, medium, high
    risk_description: str
    rework_probability: float
    potential_rework_cost: float

@dataclass
class CompressionPlan:
    target_reduction: int
    achieved_reduction: int
    crash_activities: List[Tuple[str, int]]  # (activity_id, days_crashed)
    fast_track_options: List[FastTrackOption]
    total_additional_cost: float
    new_project_duration: int
    risk_assessment: str

class ScheduleCompressor:
    """Compress construction schedules using crashing and fast-tracking."""

    def __init__(self):
        self.activities: Dict[str, Activity] = {}
        self.fast_track_options: List[FastTrackOption] = []
        self.project_duration: int = 0
        self.critical_path: List[str] = []

    def add_activity(self, id: str, name: str,
                    normal_duration: int, crash_duration: int,
                    normal_cost: float, crash_cost: float,
                    predecessors: List[str] = None,
                    is_critical: bool = False) -> Activity:
        """Add activity with crash data."""
        activity = Activity(
            id=id,
            name=name,
            normal_duration=normal_duration,
            crash_duration=crash_duration,
            normal_cost=normal_cost,
            crash_cost=crash_cost,
            predecessors=predecessors or [],
            is_critical=is_critical
        )
        self.activities[id] = activity
        return activity

    def add_fast_track_option(self, activity1_id: str, activity2_id: str,
                             overlap_days: int, risk_level: str,
                             risk_description: str,
                             rework_probability: float = 0.1,
                             potential_rework_cost: float = 0) -> FastTrackOption:
        """Add fast-tracking option between activities."""
        option = FastTrackOption(
            activity1_id=activity1_id,
            activity2_id=activity2_id,
            overlap_days=overlap_days,
            risk_level=risk_level,
            risk_description=risk_description,
            rework_probability=rework_probability,
            potential_rework_cost=potential_rework_cost
        )
        self.fast_track_options.append(option)
        return option

    def calculate_project_duration(self) -> int:
        """Calculate current project duration using CPM."""
        # Simple forward pass
        finish_times = {}

        def get_finish(act_id: str) -> int:
            if act_id in finish_times:
                return finish_times[act_id]

            act = self.activities[act_id]
            if not act.predecessors:
                start = 0
            else:
                start = max(get_finish(p) for p in act.predecessors)

            finish_times[act_id] = start + act.current_duration
            return finish_times[act_id]

        for act_id in self.activities:
            get_finish(act_id)

        self.project_duration = max(finish_times.values()) if finish_times else 0
        return self.project_duration

    def identify_critical_path(self) -> List[str]:
        """Identify critical path activities."""
        # Simplified - in practice, use full CPM
        self.calculate_project_duration()

        # Mark activities with zero float as critical
        critical = [act.id for act in self.activities.values() if act.is_critical]
        self.critical_path = critical
        return critical

    def analyze_crash_options(self) -> List[Dict]:
        """Analyze all crashing options sorted by cost efficiency."""
        crash_options = []

        for act in self.activities.values():
            if act.days_available_to_crash > 0 and act.is_critical:
                crash_options.append({
                    'activity_id': act.id,
                    'activity_name': act.name,
                    'crash_slope': act.crash_slope,
                    'max_days': act.days_available_to_crash,
                    'current_duration': act.current_duration,
                    'crash_duration': act.crash_duration
                })

        # Sort by crash slope (cost per day)
        return sorted(crash_options, key=lambda x: x['crash_slope'])

    def crash_schedule(self, target_days: int,
                      max_budget: float = float('inf')) -> CompressionPlan:
        """Crash schedule to reduce duration by target days."""
        self.calculate_project_duration()
        original_duration = self.project_duration

        crashed_activities = []
        total_cost = 0
        days_achieved = 0

        # Get crash options
        options = self.analyze_crash_options()

        while days_achieved < target_days and options:
            # Find cheapest option
            best_option = None
            for opt in options:
                if opt['max_days'] > 0:
                    best_option = opt
                    break

            if not best_option:
                break

            # Crash by 1 day
            act = self.activities[best_option['activity_id']]
            crash_cost = act.crash_slope

            if total_cost + crash_cost > max_budget:
                break

            act.current_duration -= 1
            total_cost += crash_cost
            days_achieved += 1

            # Update option
            best_option['max_days'] -= 1

            # Track what was crashed
            existing = next((c for c in crashed_activities if c[0] == act.id), None)
            if existing:
                crashed_activities.remove(existing)
                crashed_activities.append((act.id, existing[1] + 1))
            else:
                crashed_activities.append((act.id, 1))

            # Refresh options (critical path may change)
            options = self.analyze_crash_options()

        new_duration = self.calculate_project_duration()

        return CompressionPlan(
            target_reduction=target_days,
            achieved_reduction=days_achieved,
            crash_activities=crashed_activities,
            fast_track_options=[],
            total_additional_cost=total_cost,
            new_project_duration=new_duration,
            risk_assessment="Low risk - crashing uses proven methods"
        )

    def fast_track_schedule(self, target_days: int,
                           max_risk: str = "medium") -> CompressionPlan:
        """Fast-track schedule by overlapping activities."""
        risk_order = {"low": 1, "medium": 2, "high": 3}
        max_risk_level = risk_order.get(max_risk, 2)

        # Filter options by risk level
        viable_options = [
            opt for opt in self.fast_track_options
            if risk_order.get(opt.risk_level, 3) <= max_risk_level
        ]

        # Sort by overlap (most time saved first)
        viable_options.sort(key=lambda x: -x.overlap_days)

        selected_options = []
        total_overlap = 0
        total_risk_cost = 0

        for opt in viable_options:
            if total_overlap >= target_days:
                break

            selected_options.append(opt)
            total_overlap += opt.overlap_days
            total_risk_cost += opt.rework_probability * opt.potential_rework_cost

        self.calculate_project_duration()
        new_duration = self.project_duration - total_overlap

        risk_text = "High risk" if max_risk == "high" else "Moderate risk" if max_risk == "medium" else "Low risk"

        return CompressionPlan(
            target_reduction=target_days,
            achieved_reduction=total_overlap,
            crash_activities=[],
            fast_track_options=selected_options,
            total_additional_cost=total_risk_cost,
            new_project_duration=new_duration,
            risk_assessment=f"{risk_text} - potential rework if predecessor changes"
        )

    def optimize_compression(self, target_days: int,
                            max_budget: float,
                            max_risk: str = "medium") -> CompressionPlan:
        """Find optimal combination of crashing and fast-tracking."""
        # Try crash-only
        crash_plan = self.crash_schedule(target_days, max_budget)

        if crash_plan.achieved_reduction >= target_days:
            return crash_plan

        # Need additional fast-tracking
        remaining_days = target_days - crash_plan.achieved_reduction
        remaining_budget = max_budget - crash_plan.total_additional_cost

        fast_track_plan = self.fast_track_schedule(remaining_days, max_risk)

        # Combine plans
        total_reduction = crash_plan.achieved_reduction + fast_track_plan.achieved_reduction
        total_cost = crash_plan.total_additional_cost + fast_track_plan.total_additional_cost

        return CompressionPlan(
            target_reduction=target_days,
            achieved_reduction=total_reduction,
            crash_activities=crash_plan.crash_activities,
            fast_track_options=fast_track_plan.fast_track_options,
            total_additional_cost=total_cost,
            new_project_duration=self.project_duration - total_reduction,
            risk_assessment="Combined approach - balance of cost and risk"
        )

    def generate_cost_curve(self, max_compression: int) -> List[Dict]:
        """Generate time-cost tradeoff curve."""
        curve = []
        self.calculate_project_duration()
        original_duration = self.project_duration

        # Reset all activities to normal
        for act in self.activities.values():
            act.current_duration = act.normal_duration

        base_cost = sum(act.normal_cost for act in self.activities.values())

        curve.append({
            'duration': original_duration,
            'cost': base_cost,
            'compression': 0
        })

        for days in range(1, max_compression + 1):
            # Reset and crash by 'days'
            for act in self.activities.values():
                act.current_duration = act.normal_duration

            plan = self.crash_schedule(days)

            if plan.achieved_reduction < days:
                break

            curve.append({
                'duration': plan.new_project_duration,
                'cost': base_cost + plan.total_additional_cost,
                'compression': days
            })

        return curve

    def generate_compression_report(self, plan: CompressionPlan) -> str:
        """Generate compression analysis report."""
        lines = [
            "# Schedule Compression Report",
            "",
            f"**Target Reduction:** {plan.target_reduction} days",
            f"**Achieved Reduction:** {plan.achieved_reduction} days",
            f"**New Duration:** {plan.new_project_duration} days",
            f"**Additional Cost:** ${plan.total_additional_cost:,.0f}",
            "",
            f"## Risk Assessment",
            f"{plan.risk_assessment}",
            ""
        ]

        if plan.crash_activities:
            lines.append("## Crashed Activities")
            lines.append("")
            lines.append("| Activity | Days Crashed | Cost Impact |")
            lines.append("|----------|--------------|-------------|")
            for act_id, days in plan.crash_activities:
                act = self.activities[act_id]
                cost = days * act.crash_slope
                lines.append(f"| {act.name} | {days} | ${cost:,.0f} |")
            lines.append("")

        if plan.fast_track_options:
            lines.append("## Fast-Tracked Activities")
            lines.append("")
            for opt in plan.fast_track_options:
                lines.append(f"- **{opt.activity1_id} → {opt.activity2_id}**: {opt.overlap_days} days overlap")
                lines.append(f"  - Risk: {opt.risk_level} - {opt.risk_description}")
            lines.append("")

        return "\n".join(lines)

Quick Start

# Initialize compressor
compressor = ScheduleCompressor()

# Add activities with crash data
compressor.add_activity(
    "A", "Foundation",
    normal_duration=20, crash_duration=15,
    normal_cost=100000, crash_cost=130000,
    is_critical=True
)
compressor.add_activity(
    "B", "Steel Erection",
    normal_duration=30, crash_duration=22,
    normal_cost=200000, crash_cost=260000,
    predecessors=["A"],
    is_critical=True
)
compressor.add_activity(
    "C", "MEP Rough-in",
    normal_duration=25, crash_duration=20,
    normal_cost=150000, crash_cost=180000,
    predecessors=["B"],
    is_critical=True
)

# Add fast-track options
compressor.add_fast_track_option(
    "A", "B", overlap_days=5,
    risk_level="medium",
    risk_description="Steel may need rework if foundation changes",
    rework_probability=0.15,
    potential_rework_cost=30000
)

# Analyze crash options
print("Crash Options (sorted by cost/day):")
for opt in compressor.analyze_crash_options():
    print(f"  {opt['activity_name']}: ${opt['crash_slope']:.0f}/day, max {opt['max_days']} days")

# Compress schedule by 15 days
plan = compressor.optimize_compression(
    target_days=15,
    max_budget=80000,
    max_risk="medium"
)

print(compressor.generate_compression_report(plan))

# Generate cost curve
curve = compressor.generate_cost_curve(20)
for point in curve:
    print(f"Duration: {point['duration']}d, Cost: ${point['cost']:,.0f}")

Requirements

pip install (no external dependencies)

Reviews

No reviews yet. Tell others what you thought.

Comments

No login needed. Share how it worked for you, ask a question, or note where it did not run.

No comments yet. Be the first to write one.

Comments are published right away. Do not include personal information such as email addresses or phone numbers. Up to 2 URLs.

0 / 1,000 characters

This form is protected by reCAPTCHA, and the Google Privacy Policy and Terms of Service apply.

More skills from this repository

Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

Analyze 5000+ IFC and Revit projects at scale for patterns, benchmarks, and insights. Big data analysis for construction.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

Check construction AI systems against the EU AI Act (Regulation 2024/1689): classify risk of estimation, scheduling, CV and agent tools, document transparency, keep human oversight. Use when deploying or auditing AI in construction.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

Orchestrate multiple AI agents for construction workflows: estimator, scheduler, document, QA and safety agents coordinated by a supervisor agent, with human checkpoints. Use when automating end-to-end project processes with agentic AI.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

Create Apache Airflow DAGs for construction data pipelines. Orchestrate ETL, validation, and reporting workflows.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

Manage as-built documentation for project closeout. Track drawing markups, coordinate updates, and verify completeness.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction355Updated Aug 22, 2026

See all skills by datadrivenconstruction

Report a problem with this skill