Schedule Delay Analyzer

Technical Implementation

import pandas as pd
from datetime import date, timedelta
from typing import Dict, Any, List, Optional
from dataclasses import dataclass, field
from enum import Enum


class DelayType(Enum):
    EXCUSABLE_COMPENSABLE = "excusable_compensable"
    EXCUSABLE_NON_COMPENSABLE = "excusable_non_compensable"
    NON_EXCUSABLE = "non_excusable"
    CONCURRENT = "concurrent"


class DelayCause(Enum):
    OWNER_CHANGE = "owner_change"
    DESIGN_ERROR = "design_error"
    WEATHER = "weather"
    DIFFERING_CONDITIONS = "differing_conditions"
    CONTRACTOR_ISSUE = "contractor_issue"
    MATERIAL_DELAY = "material_delay"
    LABOR_SHORTAGE = "labor_shortage"
    PERMIT_DELAY = "permit_delay"
    OTHER = "other"


@dataclass
class DelayEvent:
    delay_id: str
    activity_id: str
    activity_name: str
    delay_type: DelayType
    cause: DelayCause
    start_date: date
    end_date: date
    delay_days: int
    on_critical_path: bool
    description: str
    documentation: List[str] = field(default_factory=list)
    cost_impact: float = 0.0


@dataclass
class ScheduleBaseline:
    baseline_date: date
    planned_completion: date
    activities: Dict[str, Dict[str, date]]  # activity_id: {start, end}


class ScheduleDelayAnalyzer:
    def __init__(self, project_name: str, contract_completion: date):
        self.project_name = project_name
        self.contract_completion = contract_completion
        self.baselines: List[ScheduleBaseline] = []
        self.delays: Dict[str, DelayEvent] = {}
        self._counter = 0

    def add_baseline(self, baseline_date: date, planned_completion: date,
                    activities: Dict[str, Dict[str, date]]):
        baseline = ScheduleBaseline(baseline_date, planned_completion, activities)
        self.baselines.append(baseline)

    def record_delay(self, activity_id: str, activity_name: str,
                    delay_type: DelayType, cause: DelayCause,
                    start_date: date, end_date: date,
                    on_critical_path: bool, description: str,
                    cost_impact: float = 0) -> DelayEvent:
        self._counter += 1
        delay_id = f"DLY-{self._counter:04d}"

        delay = DelayEvent(
            delay_id=delay_id,
            activity_id=activity_id,
            activity_name=activity_name,
            delay_type=delay_type,
            cause=cause,
            start_date=start_date,
            end_date=end_date,
            delay_days=(end_date - start_date).days,
            on_critical_path=on_critical_path,
            description=description,
            cost_impact=cost_impact
        )
        self.delays[delay_id] = delay
        return delay

    def calculate_project_delay(self) -> int:
        """Calculate total critical path delay."""
        critical_delays = [d for d in self.delays.values() if d.on_critical_path]
        return sum(d.delay_days for d in critical_delays)

    def analyze_by_type(self) -> Dict[str, Dict[str, Any]]:
        analysis = {}
        for delay in self.delays.values():
            dtype = delay.delay_type.value
            if dtype not in analysis:
                analysis[dtype] = {'count': 0, 'days': 0, 'cost': 0}
            analysis[dtype]['count'] += 1
            analysis[dtype]['days'] += delay.delay_days
            analysis[dtype]['cost'] += delay.cost_impact
        return analysis

    def analyze_by_cause(self) -> Dict[str, int]:
        by_cause = {}
        for delay in self.delays.values():
            cause = delay.cause.value
            by_cause[cause] = by_cause.get(cause, 0) + delay.delay_days
        return by_cause

    def calculate_time_extension_claim(self) -> Dict[str, Any]:
        """Calculate basis for time extension claim."""
        excusable = [d for d in self.delays.values()
                    if d.delay_type in [DelayType.EXCUSABLE_COMPENSABLE,
                                        DelayType.EXCUSABLE_NON_COMPENSABLE]
                    and d.on_critical_path]

        compensable = [d for d in excusable
                      if d.delay_type == DelayType.EXCUSABLE_COMPENSABLE]

        return {
            'excusable_delays': len(excusable),
            'excusable_days': sum(d.delay_days for d in excusable),
            'compensable_delays': len(compensable),
            'compensable_days': sum(d.delay_days for d in compensable),
            'total_cost_impact': sum(d.cost_impact for d in compensable),
            'recommended_extension': sum(d.delay_days for d in excusable)
        }

    def get_summary(self) -> Dict[str, Any]:
        critical_delay = self.calculate_project_delay()
        projected_completion = self.contract_completion + timedelta(days=critical_delay)

        return {
            'project': self.project_name,
            'contract_completion': self.contract_completion,
            'projected_completion': projected_completion,
            'total_delays': len(self.delays),
            'critical_path_delays': sum(1 for d in self.delays.values() if d.on_critical_path),
            'total_delay_days': critical_delay,
            'by_type': self.analyze_by_type(),
            'by_cause': self.analyze_by_cause()
        }

    def export_analysis(self, output_path: str):
        data = [{
            'ID': d.delay_id,
            'Activity': d.activity_name,
            'Type': d.delay_type.value,
            'Cause': d.cause.value,
            'Start': d.start_date,
            'End': d.end_date,
            'Days': d.delay_days,
            'Critical': d.on_critical_path,
            'Cost Impact': d.cost_impact,
            'Description': d.description
        } for d in self.delays.values()]
        pd.DataFrame(data).to_excel(output_path, index=False)

Quick Start

analyzer = ScheduleDelayAnalyzer("Office Tower", date(2024, 12, 31))

delay = analyzer.record_delay(
    activity_id="A-300",
    activity_name="Foundation Work",
    delay_type=DelayType.EXCUSABLE_COMPENSABLE,
    cause=DelayCause.OWNER_CHANGE,
    start_date=date(2024, 3, 1),
    end_date=date(2024, 3, 15),
    on_critical_path=True,
    description="Owner requested additional scope",
    cost_impact=50000
)

summary = analyzer.get_summary()
print(f"Project delayed by {summary['total_delay_days']} days")

claim = analyzer.calculate_time_extension_claim()
print(f"Recommended extension: {claim['recommended_extension']} days")

Resources

  • DDC Book: Chapter 3.3 - Schedule Management

Reviews

No reviews yet. Tell others what you thought.

Comments

No login needed. Share how it worked for you, ask a question, or note where it did not run.

No comments yet. Be the first to write one.

Comments are published right away. Do not include personal information such as email addresses or phone numbers. Up to 2 URLs.

0 / 1,000 characters

This form is protected by reCAPTCHA, and the Google Privacy Policy and Terms of Service apply.

More skills from this repository

Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

Analyze 5000+ IFC and Revit projects at scale for patterns, benchmarks, and insights. Big data analysis for construction.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

Check construction AI systems against the EU AI Act (Regulation 2024/1689): classify risk of estimation, scheduling, CV and agent tools, document transparency, keep human oversight. Use when deploying or auditing AI in construction.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

Orchestrate multiple AI agents for construction workflows: estimator, scheduler, document, QA and safety agents coordinated by a supervisor agent, with human checkpoints. Use when automating end-to-end project processes with agentic AI.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

Create Apache Airflow DAGs for construction data pipelines. Orchestrate ETL, validation, and reporting workflows.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

Automate as-built documentation and digital handover for construction. Compile project records, generate O&M manuals, create asset databases, and ensure complete project closeout.

The English summary is being prepared. Showing the original description.

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction359Updated Oct 20, 2026

See all skills by datadrivenconstruction

Report a problem with this skill