Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact. Use when asked to write a change order, price extra work, draft a CO or COR/PCO, respond to a directive for changed work, or paper a field change. Produces a complete change order request with contract-clause entitlement, labour/material/equipment/OH&P breakdown, time impact statement, and reservation of rights.

The English summary is being prepared. Showing the original description.

Run score Not tested

See how to install

Files included (1)

  • SKILL.md5.8 KB

SKILL.md (original)

Review the instructions the agent will receive before you install.

Change Order Writer Skill

A change order that just says "extra work — $48,500" gets cut in half in review. A defensible one answers three questions before they're asked: why am I entitled (which contract clause, triggered by what event), what exactly changed (scope delta from the contract baseline), and what does it really cost (built-up pricing plus time). This skill drafts change orders that survive an owner's rep audit — and preserves rights on the impacts you can't price yet.

What This Skill Produces

  • A complete change order request (COR/PCO) ready for letterhead
  • Entitlement narrative citing the contract clause and the triggering event/document
  • Scope delta — contract baseline vs. changed condition, with document references
  • Pricing breakdown: labour, material, equipment, subcontractor cost, then OH&P per the contract markup provisions
  • Schedule impact statement and a reservation of rights for cumulative/unquantified impacts

Required Inputs

Ask for what's missing; from a thin brief, draft anyway and mark every gap [confirm]:

  • The change event — what happened (RFI answer, design revision, differing site condition, owner directive, regulatory change) and when it was discovered
  • Contract references — changes clause number, notice requirements, allowed markup percentages, unit rates if any
  • Baseline scope — what the contract documents required before the change
  • Cost inputs — crew composition, hours, material quantities/quotes, equipment, sub quotes (rough is fine; the skill structures them)
  • Schedule situation — is affected work on or near the critical path; current completion date

Entitlement & Pricing Framework

Entitlement first. Classify the trigger — it drives the clause you cite:

TriggerTypical basis
Owner/architect directive or design revisionChanges clause (e.g. AIA A201 §7 / EJCDC / contract equivalent)
Differing site conditionDSC clause — Type I (differs from documents) or Type II (unusual for the locality)
RFI answer adding workChanges clause via the RFI/ASI as the directive document
Owner-caused delay/interferenceChanges + delay provisions (pair with a delay notice)

Never assert entitlement without naming the clause and the triggering document by number and date. If notice deadlines have passed, say so and frame the submission accordingly — don't hide it.

Pricing build-up. Price from records, not round numbers: labour (crew × hours × loaded rates — base plus burden), material (quantities × quoted prices, attach quotes), equipment (owned at established rates, rented at invoice), subcontractor cost, then apply OH&P at the contract-specified markups on self-performed and sub work separately. Include small-tools/consumables, supervision, and bond/insurance adjustment if the contract allows. Anything estimated rather than quoted gets labelled.

Time. State added work duration and whether it hits the critical path. If time impact can't be fixed yet, request a to-be-determined extension and reserve rights — never write "no schedule impact" as a default.

Output Format

Change Order Request No. [#]: [Short title]

Project / Contract No. / Date / To / From 1. Description of change — plain-language summary of the changed condition. 2. Entitlement — clause citation + triggering document (RFI #, ASI #, directive, DSC discovery date) + notice given (date, method). 3. Scope delta — was/is table against contract documents. 4. Pricing — itemised table: Labour / Material / Equipment / Subcontractors / Subtotal / OH&P (per §[x]) / Bond & insurance / Total. Attachments list (quotes, tickets, T&M sheets). 5. Schedule impact — [X] calendar days requested, critical-path basis stated, or expressly reserved pending analysis. 6. Reservation of rights — rights reserved for cumulative impact, acceleration, and consequential effects not quantifiable at submission. 7. Signature block and the line: "This draft is not legal advice — route through your contracts counsel before sending."

Quality Checks

  • Entitlement cites a specific clause number and a specific triggering document with date
  • Notice status is stated honestly — given on time, late, or being given by this submission
  • Every cost line is either backed by a record/quote or labelled as an estimate [confirm]
  • OH&P follows the contract markup provisions, not a default percentage
  • Schedule impact is affirmatively stated or expressly reserved — never silent
  • Reservation of rights and the not-legal-advice routing line are present

Anti-Patterns

  • Do not price a change order from bare cost without OH&P and a cumulative-impact reservation — you won't get a second bite
  • Do not write "no schedule impact" reflexively to look cooperative — silence waives time you may need
  • Do not proceed with changed work on a verbal directive without papering it the same day
  • Do not bundle unrelated changes into one CO — each event stands on its own entitlement
  • Do not soften entitlement language ("we feel", "we believe we may be due") — state the clause and the facts

Example Trigger Phrases

  • "Write a change order."
  • "Price extra work."
  • "Draft a CO or COR/PCO."
  • "Respond to a directive for changed work."
  • "Paper a field change."

Reviews

No reviews yet. Tell others what you thought.

Comments

No login needed. Share how it worked for you, ask a question, or note where it did not run.

No comments yet. Be the first to write one.

Comments are published right away. Do not include personal information such as email addresses or phone numbers. Up to 2 URLs.

0 / 1,000 characters

This form is protected by reCAPTCHA, and the Google Privacy Policy and Terms of Service apply.

More skills from this repository

Design a 360-degree feedback survey or write a structured 360 feedback report. Use when asked to build a 360 feedback process, write 360 feedback for a colleague, design a feedback survey, or produce a feedback report. Produces either a complete survey instrument with rating scales and open-ended questions, or a structured narrative feedback report with themes, strengths, and development areas.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

Decode a 401k or workplace retirement plan — the real cost of its funds, the match's fine print, vesting math, and the plan features worth using or avoiding. Use when someone asks 'is my 401k any good', 'decode my 401k plan', 'which funds should I look at', or 'what fees am I paying'. Produces a fee decode in dollars-over-time, match and vesting math, a fund-lineup triage by cost, and the questions for HR or the plan administrator.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

Design statistically rigorous A/B tests for product features, UI changes, onboarding flows, and pricing experiments. Use when asked to set up an experiment, design an A/B test, calculate sample size, or interpret test results. Produces a complete test plan with hypothesis, variant definitions, sample size, duration estimate, guardrail metrics, and a results interpretation guide.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

Analyse a finished A/B test and write the readout — the result, whether it's statistically and practically significant, what it means, and the ship/no-ship call. Use when asked to analyse experiment results, write an A/B test readout, interpret test data, or decide whether to ship a variant. Produces a clear verdict with the lift and confidence, segment cuts, the risks (peeking, novelty, sample), and a recommendation. Distinct from planning a test — this reads results.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

Build or tailor an academic CV for faculty, postdoc, research or fellowship applications: publications, grants, teaching, supervision and service in the order the field expects, with consistent citations. Use when asked to write my academic CV, update my CV for a lectureship, tenure-track or postdoc application, format my publications list, or adapt my academic CV for an industry research role. Produces the full academic CV, a field-appropriate section order, a clean publications list in one citation style, and a two-page summary version when asked.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

Generate a WCAG 2.2 accessibility audit checklist and remediation suggestions for any UI or design. Use when asked to audit for accessibility, check WCAG compliance, review a design for a11y issues, or create an accessibility remediation plan. Produces a prioritised checklist with pass/fail assessments and specific fixes.

The English summary is being prepared. Showing the original description.

mohitagw15856/pm-claude-skills1.5KUpdated Oct 23, 2026

See all skills by mohitagw15856

Report a problem with this skill