Skip to content
cccskills
FreePublished on GitHub

create-work-breakdown-structure

Create a Work Breakdown Structure (WBS) and WBS Dictionary from project charter deliverables. Covers hierarchical decomposition, WBS coding, effort estimation, dependency identification, and critical path candidates. Use after a project charter is approved, when planning a classic or waterfall project with defined deliverables, breaking a large initiative into manageable work packages, or establishing a basis for effort estimation and resource planning.

The English summary is being prepared. Showing the original description.

See how to install

Files included (1)

  • SKILL.md7.2 KB

SKILL.md (original)

Review the instructions the agent will receive before you install.

Create a Work Breakdown Structure

Decompose project scope into a hierarchical set of work packages that can be estimated, assigned, and tracked. The WBS provides the foundation for effort estimation, resource planning, and schedule development by breaking down complex deliverables into manageable components.

When to Use

  • After a project charter is approved and scope is defined
  • Planning a classic/waterfall project with defined deliverables
  • Breaking down a large initiative into manageable work packages
  • Establishing a basis for effort estimation and resource planning
  • Creating a shared understanding of all required work

Inputs

  • Required: Approved project charter (especially scope and deliverables sections)
  • Required: Project methodology (classic/waterfall, or hybrid with WBS for planning)
  • Optional: Historical effort data from similar projects
  • Optional: Team composition and available skills
  • Optional: Organizational WBS templates or standards

Procedure

Step 1: Extract Deliverables from Charter

Read the project charter. List all deliverables and acceptance criteria. Group them into 3-7 top-level categories (these become WBS Level 1 elements).

Expected: List of Level 1 WBS elements matching charter deliverables.

On failure: If charter is vague, return to draft-project-charter to refine scope.

Step 2: Decompose into Work Packages

For each Level 1 element, decompose into sub-elements (Level 2, Level 3). Apply the 100% rule: child elements must represent 100% of the parent's scope. Stop decomposing when work packages are:

  • Estimable (can assign effort in person-days)
  • Assignable (one person or team owns it)
  • Measurable (clear done/not-done criteria)

Create a WBS outline:

# Work Breakdown Structure: [Project Name]
## Document ID: WBS-[PROJECT]-[YYYY]-[NNN]

### WBS Hierarchy

1. [Level 1: Deliverable Category A]
   1.1 [Level 2: Sub-deliverable]
      1.1.1 [Level 3: Work Package]
      1.1.2 [Level 3: Work Package]
   1.2 [Level 2: Sub-deliverable]
2. [Level 1: Deliverable Category B]
   2.1 [Level 2: Sub-deliverable]
3. [Level 1: Project Management]
   3.1 Planning
   3.2 Monitoring & Control
   3.3 Closure

Apply WBS codes (1.1.1 format). Ensure 3-5 levels deep maximum. Always include a "Project Management" branch.

Expected: Complete WBS with 15-50 work packages, each with a unique WBS code.

On failure: If decomposition exceeds 5 levels, the scope is too large — consider splitting into sub-projects.

Step 3: Write WBS Dictionary

For each work package (leaf node), write a dictionary entry:

# WBS Dictionary: [Project Name]
## Document ID: WBS-DICT-[PROJECT]-[YYYY]-[NNN]

### WBS 1.1.1: [Work Package Name]
- **Description**: What this work package produces
- **Acceptance Criteria**: How to verify it's done
- **Responsible**: Person or role
- **Estimated Effort**: [T-shirt size or person-days]
- **Dependencies**: WBS codes this depends on
- **Assumptions**: Key assumptions for this work package

### WBS 1.1.2: [Work Package Name]
...

Expected: Dictionary entry for every leaf-node work package.

On failure: Missing dictionary entries indicate incomplete decomposition — revisit Step 2.

Step 4: Estimate Effort

For each work package, apply one estimation method:

  • T-shirt sizing (XS/S/M/L/XL) for early-stage planning
  • Person-days for detailed planning
  • Three-point estimate (optimistic/most likely/pessimistic) for high-uncertainty work

Create a summary table:

## Effort Summary
| WBS Code | Work Package | Estimate | Method | Confidence |
|----------|-------------|----------|--------|------------|
| 1.1.1 | [Name] | 5 pd | person-days | High |
| 1.1.2 | [Name] | M | t-shirt | Medium |

Total effort = sum of all work packages.

Expected: Every work package has an effort estimate with stated confidence.

On failure: If confidence is Low on >30% of packages, schedule a refinement session with SMEs.

Step 5: Identify Dependencies and Critical Path Candidates

Map dependencies between work packages:

## Dependencies
| WBS Code | Depends On | Type | Notes |
|----------|-----------|------|-------|
| 1.2.1 | 1.1.1 | Finish-to-Start | Output of 1.1.1 is input to 1.2.1 |
| 2.1.1 | 1.1.2 | Finish-to-Start | |

Identify the longest chain of dependent work packages — this is the critical path candidate.

Expected: Dependency table with at least finish-to-start relationships identified.

On failure: If dependencies form cycles, the decomposition has errors — revisit Step 2.

Step 6: Review and Baseline

Combine WBS and dictionary into final documents. Verify the 100% rule at every level. Get stakeholder sign-off.

Expected: WBS.md and WBS-DICTIONARY.md files created and reviewed.

On failure: If stakeholders identify missing scope, add work packages and re-estimate.

Validation

  • WBS file created with document ID and WBS codes
  • 100% rule satisfied: children fully represent parent scope at every level
  • Every leaf node has a WBS dictionary entry
  • All work packages have effort estimates
  • Dependencies identified with no circular references
  • Project Management branch included
  • Critical path candidates identified
  • WBS depth does not exceed 5 levels

Common Pitfalls

  • Confusing deliverables with activities: WBS elements should be nouns (deliverables), not verbs (activities). "User Authentication Module" not "Implement Authentication".
  • Violating the 100% rule: If children don't add up to 100% of parent scope, work will be missed.
  • Too shallow or too deep: 2 levels is too vague for planning; 6+ levels is micromanagement. Target 3-5 levels.
  • Skipping Project Management branch: PM work (planning, meetings, reporting) is real work that consumes effort.
  • Estimating before decomposing: Estimate work packages, not categories. A Level 1 estimate is unreliable.
  • No dictionary: A WBS without a dictionary is a tree of labels — the dictionary provides the definition of done.

Related Skills

  • draft-project-charter — provides the scope and deliverables that feed WBS decomposition
  • manage-backlog — translate WBS work packages into backlog items for tracking
  • generate-status-report — report progress against WBS % complete
  • plan-sprint — if using hybrid approach, sprint-plan from WBS work packages
  • conduct-retrospective — review estimation accuracy and decomposition quality

Reviews

No reviews yet. Tell others what you thought.

Comments

No login needed. Share how it worked for you, ask a question, or note where it did not run.

No comments yet. Be the first to write one.

Comments are published right away. Do not include personal information such as email addresses or phone numbers. Up to 2 URLs.

0 / 1,000 characters

This form is protected by reCAPTCHA, and the Google Privacy Policy and Terms of Service apply.

More skills from this repository

Execute structural metamorphosis using strangler fig migration, chrysalis phases, and interface preservation. Covers transformation planning, parallel running, progressive cutover, rollback design, and post-metamorphosis stabilization for system architecture evolution. Use when assess-form has classified the system as READY for transformation, when migrating from monolith to microservices, when replacing a core subsystem while dependents continue operating, or when any architectural change must be gradual rather than big-bang.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

Master skill composing the 5-step synoptic cycle for panoramic synthesis across multiple domains. Orchestrates meditate, expand-awareness, observe, awareness, integrate-gestalt, and express-insight into a coherent process that produces unified understanding rather than sequential compromise. Use when a problem genuinely spans 3+ domains and the interactions between domains matter more than depth in any one, when sequential analysis feels like compromise rather than integration, or before major architectural decisions affecting multiple stakeholders.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

Scaffold a new puzzle type across all 10+ pipeline integration points in jigsawR. Creates the core puzzle module, wires it into the unified pipeline (generation, positioning, rendering, adjacency), adds ggpuzzle geom/stat layers, updates DESCRIPTION and config.yml, extends the Shiny app, and creates a comprehensive test suite. Use when adding a completely new puzzle type to the package or following the 10-point integration checklist to ensure nothing is missed end-to-end.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

Add Rcpp or RcppArmadillo integration to an R package for high-performance C++ code. Covers setup, writing C++ functions, RcppExports generation, testing compiled code, and debugging. Use when an R function is too slow and profiling confirms a bottleneck, when you need to interface with existing C/C++ libraries, or when implementing algorithms (loops, recursion, linear algebra) that benefit from compiled code.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

aikido

Free

Practice aikido as a defensive martial art emphasizing harmony, redirection, and controlled resolution. Covers centering and grounding, ukemi (safe falling and rolling), core techniques (irimi-nage, shiho-nage, kote-gaeshi, ikkyo), blending and tai sabaki (body movement), randori (multiple attacker practice), weapons awareness, and applying principles off the mat. Use when learning a defensive martial art that prioritizes de-escalation, developing the ability to redirect aggression without causing unnecessary harm, building safe falling skills, or cultivating calm centeredness under physical pressure.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

Analyze an arbitrary codebase to identify functions, APIs, and data sources suitable for exposure as MCP tools, producing a tool specification document. Use when planning an MCP server for an existing project, auditing a codebase before wrapping it as an AI-accessible tool surface, comparing what a codebase can do versus what is already exposed via MCP, or generating a tool spec to hand off to scaffold-mcp-server.

The English summary is being prepared. Showing the original description.

pjt222/agent-almanac42Updated Oct 15, 2026

See all skills by pjt222

Report a problem with this skill