Use for day-ahead or multi-period unit commitment problems, including thermal on/off schedules, dispatch, startup/shutdown logic, minimum up/down time, ramping, spinning reserve deliverability, renewable curtailment, operating-cost accounting, and independent feasibility checks for power-system operations schedules.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

설치 방법 보기

포함된 파일(1)

  • SKILL.md8.0 KB

SKILL.md(원문)

설치하기 전에 에이전트에게 전달되는 지시 내용을 확인할 수 있습니다.

Unit Commitment Operating Rules

Use this skill when a task asks for a day-ahead or multi-period unit commitment schedule with generators, load, reserves, operating constraints, and cost tradeoffs.

This is a reusable UC operating guide. It gives formulation and validation patterns, not a complete task-specific mathematical model.

UC In One Paragraph

Unit commitment decides which generators are online over time, when they start or stop, how much they produce, and how much reserve they can physically provide. It is harder than hourly economic dispatch because startup/shutdown decisions, ramping, minimum up/down time, reserve deliverability, initial conditions, and cost curves couple one period to the next.

Keep These Concepts Separate

For each thermal unit g and period t:

u[g, t]      # commitment/on status, binary
start[g, t]  # startup transition, binary
stop[g, t]   # shutdown transition, binary
p[g, t]      # production variable: know whether actual MW or above-minimum MW
r[g, t]      # scheduled reserve

Reports often require actual MW output. Many UC models internally use output above minimum:

actual_output = pmin[g] * u[g, t] + p_above_min[g, t]
p_above_min = actual_output - pmin[g] * u[g, t]

Do not mix these conventions in ramping, reserve, cost, or reporting.

Core Feasibility Checks

Before reporting a schedule, independently verify:

  • every resource appears exactly once and all time-series have length T;
  • commitment, startup, and shutdown are binary;
  • offline thermal units have zero production and zero reserve;
  • online thermal units respect min/max output;
  • must-run units are online when required;
  • startup/shutdown indicators match commitment transitions;
  • demand balance holds in every period;
  • renewable output stays within period-specific bounds;
  • scheduled reserve meets the system requirement;
  • reserve is deliverable under headroom, startup/shutdown capability, and ramp limits;
  • minimum up/down time and initial conditions are respected;
  • cost and summary fields are recomputed from arrays.

Transition Logic

Link startup/shutdown to commitment and the initial state:

prev_u = initial_on[g] if t == 0 else u[g, t - 1]
u[g, t] - prev_u == start[g, t] - stop[g, t]
start[g, t] + stop[g, t] <= 1

Equivalent validation pattern:

prev_on = initial_on[g]
for t in range(T):
    assert start[g, t] == int(u[g, t] == 1 and prev_on == 0)
    assert stop[g, t] == int(u[g, t] == 0 and prev_on == 1)
    prev_on = u[g, t]

Capacity And Offline Zeroes

For actual-MW production:

pmin[g] * u[g, t] <= production[g, t] <= pmax[g] * u[g, t]
0 <= reserve[g, t]

For above-minimum production:

cap = pmax[g] - pmin[g]
0 <= p_above_min[g, t] <= cap * u[g, t]
0 <= reserve[g, t]

If u[g, t] == 0, both production and reserve must be zero.

Demand, Renewables, And System Reserve

Use the task's system/zone/network convention. For a single-zone system:

thermal_gen = sum(actual_thermal[g, t] for g in thermal_units)
renew_gen = sum(renewable_output[r, t] for r in renewable_units)
assert abs(thermal_gen + renew_gen - demand[t]) <= tol
assert sum(reserve[g, t] for g in thermal_units) >= reserve_requirement[t] - tol

Renewables:

renewable_min[r, t] <= renewable_output[r, t] <= renewable_max[r, t]

If min equals max, output is fixed. If curtailment is allowed, output may be below max. Do not count renewable headroom as spinning reserve unless the prompt explicitly allows it.

Reserve Deliverability

Reserve is not just unused nameplate capacity. Production and reserve compete for the same physical capability, and reserve must be deployable.

Headroom-only checks are too weak:

# Not enough by itself:
reserve[g, t] <= pmax[g] - production[g, t]
reserve[g, t] <= ramp_up[g]

Use joint production-plus-reserve checks. With actual-MW production:

production[g, t] + reserve[g, t] <= pmax[g] * u[g, t]

With above-minimum production:

p_above_min[g, t] + reserve[g, t] <= (pmax[g] - pmin[g]) * u[g, t]

Startup capability can tighten the startup period. If startup_limit is maximum total output during startup:

if start[g, t] == 1:
    production[g, t] + reserve[g, t] <= startup_limit[g]

A linear above-minimum pattern is:

startup_reduction = max(pmax[g] - startup_limit[g], 0.0)
p_above_min[g, t] + reserve[g, t] <= (
    (pmax[g] - pmin[g]) * u[g, t]
    - startup_reduction * start[g, t]
)

Apply analogous shutdown-period or pre-shutdown capability rules when the data and prompt require them.

Ramping

Use initial output/status for the first period. When reserve must be deliverable, ramp-up usually applies to production plus reserve:

previous = initial_above_min[g] if t == 0 else p_above_min[g, t - 1]
p_above_min[g, t] + reserve[g, t] - previous <= ramp_up[g]
previous - p_above_min[g, t] <= ramp_down[g]

If your model uses actual production, convert consistently before applying above-minimum ramp checks. Recheck ramping after any dispatch or repair step.

Minimum Up/Down Time

Minimum up/down constraints are time-window constraints triggered by starts/stops. Validation pattern:

if start[g, t] == 1:
    for tau in range(t, min(T, t + min_up[g])):
        assert u[g, tau] == 1

if stop[g, t] == 1:
    for tau in range(t, min(T, t + min_down[g])):
        assert u[g, tau] == 0

Account for pre-horizon time already on/off. Follow the prompt on whether post-horizon obligations are enforced.

Startup Costs

Startup cost may depend on prior offline duration. A common tier rule is largest lag not exceeding prior offline duration:

def choose_startup_cost(tiers, offline_duration):
    tiers = sorted(tiers, key=lambda z: z["lag"])
    chosen = tiers[0]
    for tier in tiers:
        if tier["lag"] <= offline_duration:
            chosen = tier
        else:
            break
    return chosen["cost"]

Update offline duration from initial status and the commitment trajectory. Be careful: duration should describe time offline before the startup period.

Production Costs

Use only cost components present in the data or required by the prompt. Do not invent no-load, reserve, curtailment, shutdown, or ramping costs.

For total-cost breakpoints:

def total_cost_from_curve(points, output_mw):
    pts = sorted((p["mw"], p["cost"]) for p in points)
    if output_mw <= pts[0][0]:
        return pts[0][1]
    if output_mw >= pts[-1][0]:
        return pts[-1][1]
    for (x0, y0), (x1, y1) in zip(pts, pts[1:]):
        if x0 <= output_mw <= x1:
            return y0 + (output_mw - x0) * (y1 - y0) / (x1 - x0)
    raise ValueError("output outside curve")

If the first point is at minimum output, its cost may represent online minimum-output cost. Do not add another fixed online cost unless the data says so.

Implementation Workflow

  1. Parse and normalize resource/time arrays.
  2. Choose actual-output or above-minimum internal variables and stick to it.
  3. Include hard feasibility constraints before optimizing cost.
  4. Extract the solution into the report convention.
  5. Run independent validation on extracted arrays.
  6. Recompute costs and summaries from arrays.
  7. Write "pass" checks only after validation passes.

Common Pitfalls

  • Treating UC as independent hourly dispatch.
  • Counting reserve from offline units or renewable headroom.
  • Checking reserve headroom but forgetting startup or ramp deliverability.
  • Ignoring initial output in first-period ramping.
  • Ignoring initial on/off duration in minimum up/down constraints.
  • Trusting a repair LP that omits a constraint family.
  • Hard-coding "pass" fields before validation.

리뷰

아직 리뷰가 없습니다. 사용해 본 소감을 남겨 주세요.

댓글

로그인 없이 쓸 수 있습니다. 사용 후기, 질문, 작동하지 않은 환경 등을 편하게 남겨 주세요.

아직 댓글이 없습니다. 첫 댓글을 남겨 보세요.

보내면 바로 공개됩니다. 이메일 주소나 전화번호 같은 개인 정보는 쓰지 마세요. URL은 2개까지입니다.

0 / 1,000자

이 양식은 reCAPTCHA로 보호되며 Google 개인정보처리방침 및 서비스 약관이 적용됩니다.

같은 저장소의 스킬

Perform various data analysis on SEC 13-F and obtain some insights of fund activities such as number of holdings, AUM, and change of holdings between two quarters.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

AC branch pi-model power flow equations (P/Q and |S|) with transformer tap ratio and phase shift, matching `acopf-math-model.md` and MATPOWER branch fields. Use when computing branch flows in either direction, aggregating bus injections for nodal balance, checking MVA (rateA) limits, computing branch loading %, or debugging sign/units issues in AC power flow.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

Redact text from PDF documents for blind review anonymization

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

Use when checking simplified ADA-derived plan-view bathroom accessibility constraints such as turning space, door clear width, toilet centerline, grab bars, and lavatory knee/toe clearance.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

Analyze failed GitHub Action jobs for a pull request.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

Use when extracting plan-view architectural geometry from DXF files with semantic CAD layers, especially when outputs must normalize rooms, doors, fixtures, clearances, and grab bars into machine-checkable JSON.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

benchflow-ai/skillsbench1.9천2026년 10월 13일 업데이트

benchflow-ai의 스킬 모두 보기

이 스킬의 문제 신고