Draft a defensible construction change order with entitlement basis, scope delta, itemised pricing, and schedule impact. Use when asked to write a change order, price extra work, draft a CO or COR/PCO, respond to a directive for changed work, or paper a field change. Produces a complete change order request with contract-clause entitlement, labour/material/equipment/OH&P breakdown, time impact statement, and reservation of rights.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

실행 점수 미검증

설치 방법 보기

포함된 파일(1)

  • SKILL.md5.8 KB

SKILL.md(원문)

설치하기 전에 에이전트에게 전달되는 지시 내용을 확인할 수 있습니다.

Change Order Writer Skill

A change order that just says "extra work — $48,500" gets cut in half in review. A defensible one answers three questions before they're asked: why am I entitled (which contract clause, triggered by what event), what exactly changed (scope delta from the contract baseline), and what does it really cost (built-up pricing plus time). This skill drafts change orders that survive an owner's rep audit — and preserves rights on the impacts you can't price yet.

What This Skill Produces

  • A complete change order request (COR/PCO) ready for letterhead
  • Entitlement narrative citing the contract clause and the triggering event/document
  • Scope delta — contract baseline vs. changed condition, with document references
  • Pricing breakdown: labour, material, equipment, subcontractor cost, then OH&P per the contract markup provisions
  • Schedule impact statement and a reservation of rights for cumulative/unquantified impacts

Required Inputs

Ask for what's missing; from a thin brief, draft anyway and mark every gap [confirm]:

  • The change event — what happened (RFI answer, design revision, differing site condition, owner directive, regulatory change) and when it was discovered
  • Contract references — changes clause number, notice requirements, allowed markup percentages, unit rates if any
  • Baseline scope — what the contract documents required before the change
  • Cost inputs — crew composition, hours, material quantities/quotes, equipment, sub quotes (rough is fine; the skill structures them)
  • Schedule situation — is affected work on or near the critical path; current completion date

Entitlement & Pricing Framework

Entitlement first. Classify the trigger — it drives the clause you cite:

TriggerTypical basis
Owner/architect directive or design revisionChanges clause (e.g. AIA A201 §7 / EJCDC / contract equivalent)
Differing site conditionDSC clause — Type I (differs from documents) or Type II (unusual for the locality)
RFI answer adding workChanges clause via the RFI/ASI as the directive document
Owner-caused delay/interferenceChanges + delay provisions (pair with a delay notice)

Never assert entitlement without naming the clause and the triggering document by number and date. If notice deadlines have passed, say so and frame the submission accordingly — don't hide it.

Pricing build-up. Price from records, not round numbers: labour (crew × hours × loaded rates — base plus burden), material (quantities × quoted prices, attach quotes), equipment (owned at established rates, rented at invoice), subcontractor cost, then apply OH&P at the contract-specified markups on self-performed and sub work separately. Include small-tools/consumables, supervision, and bond/insurance adjustment if the contract allows. Anything estimated rather than quoted gets labelled.

Time. State added work duration and whether it hits the critical path. If time impact can't be fixed yet, request a to-be-determined extension and reserve rights — never write "no schedule impact" as a default.

Output Format

Change Order Request No. [#]: [Short title]

Project / Contract No. / Date / To / From 1. Description of change — plain-language summary of the changed condition. 2. Entitlement — clause citation + triggering document (RFI #, ASI #, directive, DSC discovery date) + notice given (date, method). 3. Scope delta — was/is table against contract documents. 4. Pricing — itemised table: Labour / Material / Equipment / Subcontractors / Subtotal / OH&P (per §[x]) / Bond & insurance / Total. Attachments list (quotes, tickets, T&M sheets). 5. Schedule impact — [X] calendar days requested, critical-path basis stated, or expressly reserved pending analysis. 6. Reservation of rights — rights reserved for cumulative impact, acceleration, and consequential effects not quantifiable at submission. 7. Signature block and the line: "This draft is not legal advice — route through your contracts counsel before sending."

Quality Checks

  • Entitlement cites a specific clause number and a specific triggering document with date
  • Notice status is stated honestly — given on time, late, or being given by this submission
  • Every cost line is either backed by a record/quote or labelled as an estimate [confirm]
  • OH&P follows the contract markup provisions, not a default percentage
  • Schedule impact is affirmatively stated or expressly reserved — never silent
  • Reservation of rights and the not-legal-advice routing line are present

Anti-Patterns

  • Do not price a change order from bare cost without OH&P and a cumulative-impact reservation — you won't get a second bite
  • Do not write "no schedule impact" reflexively to look cooperative — silence waives time you may need
  • Do not proceed with changed work on a verbal directive without papering it the same day
  • Do not bundle unrelated changes into one CO — each event stands on its own entitlement
  • Do not soften entitlement language ("we feel", "we believe we may be due") — state the clause and the facts

Example Trigger Phrases

  • "Write a change order."
  • "Price extra work."
  • "Draft a CO or COR/PCO."
  • "Respond to a directive for changed work."
  • "Paper a field change."

리뷰

아직 리뷰가 없습니다. 사용해 본 소감을 남겨 주세요.

댓글

로그인 없이 쓸 수 있습니다. 사용 후기, 질문, 작동하지 않은 환경 등을 편하게 남겨 주세요.

아직 댓글이 없습니다. 첫 댓글을 남겨 보세요.

보내면 바로 공개됩니다. 이메일 주소나 전화번호 같은 개인 정보는 쓰지 마세요. URL은 2개까지입니다.

0 / 1,000자

이 양식은 reCAPTCHA로 보호되며 Google 개인정보처리방침 및 서비스 약관이 적용됩니다.

같은 저장소의 스킬

Design a 360-degree feedback survey or write a structured 360 feedback report. Use when asked to build a 360 feedback process, write 360 feedback for a colleague, design a feedback survey, or produce a feedback report. Produces either a complete survey instrument with rating scales and open-ended questions, or a structured narrative feedback report with themes, strengths, and development areas.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

Decode a 401k or workplace retirement plan — the real cost of its funds, the match's fine print, vesting math, and the plan features worth using or avoiding. Use when someone asks 'is my 401k any good', 'decode my 401k plan', 'which funds should I look at', or 'what fees am I paying'. Produces a fee decode in dollars-over-time, match and vesting math, a fund-lineup triage by cost, and the questions for HR or the plan administrator.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

Design statistically rigorous A/B tests for product features, UI changes, onboarding flows, and pricing experiments. Use when asked to set up an experiment, design an A/B test, calculate sample size, or interpret test results. Produces a complete test plan with hypothesis, variant definitions, sample size, duration estimate, guardrail metrics, and a results interpretation guide.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

Analyse a finished A/B test and write the readout — the result, whether it's statistically and practically significant, what it means, and the ship/no-ship call. Use when asked to analyse experiment results, write an A/B test readout, interpret test data, or decide whether to ship a variant. Produces a clear verdict with the lift and confidence, segment cuts, the risks (peeking, novelty, sample), and a recommendation. Distinct from planning a test — this reads results.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

Build or tailor an academic CV for faculty, postdoc, research or fellowship applications: publications, grants, teaching, supervision and service in the order the field expects, with consistent citations. Use when asked to write my academic CV, update my CV for a lectureship, tenure-track or postdoc application, format my publications list, or adapt my academic CV for an industry research role. Produces the full academic CV, a field-appropriate section order, a clean publications list in one citation style, and a two-page summary version when asked.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

Generate a WCAG 2.2 accessibility audit checklist and remediation suggestions for any UI or design. Use when asked to audit for accessibility, check WCAG compliance, review a design for a11y issues, or create an accessibility remediation plan. Produces a prioritised checklist with pass/fail assessments and specific fixes.

한국어 요약은 준비 중입니다. 원문 설명을 표시하고 있습니다.

mohitagw15856/pm-claude-skills1.5천2026년 10월 23일 업데이트

mohitagw15856의 스킬 모두 보기

이 스킬의 문제 신고