DAG Task Scheduler

Use to construct a feasible plan from declared work. State the objective, task IDs, hard edges, durations, resource classes/capacities, calendars, gates, and selection policy. It does not execute tasks, infer completion, grant authority, or claim an optimal schedule.

A forecast simulates predecessor finishes using stated durations and gate assumptions. It may schedule a future conditional start; it does not assert that the corresponding evidence already exists. At execution admission, replace those assumptions with accepted observed evidence and current resource/authority checks.

Scheduling procedure

  1. Account for every required task, hard predecessor, duration, gate, resource class, capacity, and calendar interval. A task is ready only after its hard predecessors have accepted completion evidence; dispatch is not completion. In a graphlib.TopologicalSorter-style model, call done() only after accepted completion, not when work starts.
  2. Form the ready frontier. A work-conserving ready queue can start a compatible ready task while unrelated work continues. A fixed-level barrier waits for its batch and should be used only when that synchronization is actually required.
  3. Admit a ready task only when its resource reservation and calendar interval fit. Once started, treat it as non-preemptive unless that task has a separately declared safe pause/resume contract.
  4. Record planned start/end, assigned resource, inputs, and gate evidence. On observed accepted completion, release its successors. On definite failure, block dependents unless their contracts permit absence or an independently validated replacement exists. On timeout after possible transmission, mark the effect unknown and reconcile before release, retry, or replan.
  5. Recompute only from observed state and stated policy. A changed graph, contract, or capacity assumption belongs to a versioned replanning proposal; a schedule update cannot repair invalid data or manufacture authorization.
flowchart TD
 E[Declared evidence, gates, and calendar] --> R{Hard predecessors accepted complete?}
 R -- no --> B[Blocked: missing producer or gate]
 R -- yes --> C{Compatible resource and interval available?}
 C -- no --> Q[Ready queue or report infeasible calendar]
 C -- yes --> Z[Reserve resource and planned interval]
 Z --> H{Required evidence and current authority valid?}
 H -- no --> K[Keep effect blocked; reconcile reservation]
 H -- yes --> D[Dispatch non-preemptive task]
 D --> X[Running: not graph completion]
 X --> O{Observed outcome accepted?}
 O -- completed --> N[Mark done; release successors]
 O -- definite failure --> F[Failure policy; dependents remain blocked]
 O -- timeout after possible transmission --> U[Unknown effect: reconcile before release or retry]

Four decision procedures

1. Resource contention resolution

Declare each request’s resource class, units, capacity, compatibility, duration, and calendar. Reserve feasible work; defer it when capacity/calendar cannot admit it. Priority may choose among ready compatible work, but cannot override a predecessor, approval, authority, hard budget, or calendar blackout. Do not preempt a running task merely because it is off the critical path; preemption requires a task-specific safe resume contract.

2. Wave overflow handling

When more tasks are ready than capacity allows, retain every required task in the queue and select according to a declared policy, such as deadline order, a critical-chain concern, fairness, or resource fit. “Wave” is a presentation choice, not evidence that all ready work must wait. Split into batches only because capacity or a required barrier demands it; never discard work solely because the frontier is large.

3. Priority conflicts

Compare deadlines, declared objective, resource fit, and the predecessor chain. A high-priority task blocked by a lower-priority predecessor is priority inversion evidence, not authorization to violate the edge. Document the policy used to select ready tasks and its starvation/fairness consequence. Width bounds the size of a concurrently eligible task set under the precedence model; it does not report the current ready frontier, and it does not prove makespan optimality when durations, resources, or gates differ.

4. Runtime adaptation triggers

Early accepted completion may expose eligible successors immediately. Late completion changes a forecast but does not prove a graph defect. Definite failure blocks required consumers until an allowed absence or validated replacement is established. A timeout after possible transmission is unknown: keep consumers blocked and reconcile provider/readback evidence before retrying. Replan only when graph, contract, resources, or policy must change.

Five diagnostic procedures

Wave overflow. Compare every ready request with declared capacity and resource compatibility. Queue the overflow, identify the policy selection, and report infeasibility if required work cannot fit the available calendar; no fixed multiplier proves failure.

Resource starvation. Inspect the ready frontier, availability windows, and resource fit before calling an idle slot waste. An idle CPU can be correct while the only ready work needs a human gate or a different resource class.

Priority inversion. Trace the blocking predecessor chain and its resource reservation. Adjust the ready-queue policy, reservation, or deadline expectation only without breaking hard edges or gates.

Deadline miss. Recalculate from all declared durations, predecessor chains, capacity, calendars, and gates. A critical chain can explain a miss, but it does not authorize preemption, added capacity, or skipped work unless their contracts permit them.

Thrashing schedule. Record each change, its observed trigger, and the policy revision. Repeated replanning in a chosen observation window can show instability; it does not have a universal numeric threshold. Freeze stable assignments only when the trade-off between responsiveness and disruption is declared.

Worked scheduling fixtures

Example 1: complete eight-task release plan

This constructed fixture has two identical non-preemptive compute slots and a separate one-tick human gate. One tick is one calendar day in the Gantt; it is not observed runtime.

IDOutput/taskDurationHard predecessorsResource classPlanned interval
Asource bundle with provenance2 ticks—compute[0,2)
Banalysis3 ticksAcompute[2,5)
Cpolicy review artifact2 ticksAcompute[2,4)
Drelease draft1 tickB, Ccompute[5,6)
Esecurity receipt bound to D digest2 ticksDcompute[6,8)
Gapproval bound to C and E1 tickC, Ehuman gate[8,9)
Fpublish exactly approved D digest1 tickGcompute plus authority[9,10)
Vreadback verification1 tickFcompute[10,11)

Edges are A→B, A→C, B→D, C→D, D→E, C→G, E→G, G→F, and F→V. The compute schedule is A on slot 1; B on slot 1 and C on slot 2; D, E, F, V on slot 1. G consumes the human-gate interval, not a compute slot. The chain A-B-D-E-G-F-V totals 11 ticks, so the displayed 11-tick plan is feasible and has that fixture’s critical chain. The 11-tick result is conditional on the human actually approving in that assumed interval and current action authority remaining valid. Otherwise F stays blocked. It does not prove a general optimum; elapsed time is not approval.

gantt
 title Constructed 11-tick plan; calendar dates label ticks, not runtime
 dateFormat YYYY-MM-DD
 axisFormat %m-%d
 section Compute slot 1
 A :a, 2026-01-01, 2d
 B :b, 2026-01-03, 3d
 D :d, 2026-01-06, 1d
 E :e, 2026-01-07, 2d
 F :f, 2026-01-10, 1d
 V :v, 2026-01-11, 1d
 section Compute slot 2
 C :c, 2026-01-03, 2d
 section Human gate
 G :g, 2026-01-09, 1d

Example 2: ready queue versus fixed-level barrier

After predecessor A completes at tick 0, independent B has duration 3 and C has duration 1; D has sole predecessor C and duration 1. Two compatible compute slots exist. A ready queue starts B and C at tick 0, then starts D at tick 1 while B continues through tick 3; all work completes at tick 3. A fixed-level barrier that insists on waiting for the B/C batch starts D at tick 3 and finishes at tick 4. This proves the one-tick barrier cost for this uneven-duration fixture, not a general scheduling advantage. The D output is available at tick 2 only under the ready queue.

Example 3: calendar reservation and unknown effect policy

review@r1 is ready at day 4, needs one human reviewer, and requires a one-day interval. The reviewer calendar is unavailable on days 4–5 and available on day 6, so the earliest feasible reservation is [6,7), even if a compute slot is idle. publish@p1 requires accepted r1, approval evidence, action authority, and a provider request. If the provider request times out after possible transmission, mark p1 outcome unknown; do not mark it done or release the ordinary success-dependent verify@v1. A separately authorized reconciliation/readback check may still run to resolve the unknown outcome. Reconcile provider/readback evidence: observed success records a receipt, documented definite absence plus a safe retry contract permits the same operation identity to retry, and ambiguity holds the verification consumer pending authorized resolution.

Full tables, arithmetic, and hand checks appear in worked scheduling fixtures.

Quality gates and boundaries

Before publishing a schedule, verify complete task/edge/duration accounting; hard predecessor and gate evidence; declared objective/policy; resource capacities, compatibility, and calendars; valid non-preemptive assumption; planned versus observed-state labeling; critical-chain calculation; deadline feasibility; outcome branches; and reschedule history. Report any infeasible capacity or deadline rather than filtering tasks or claiming optimality.

Do not use this skill to build or alter the DAG, execute work, monitor runtime, process results, diagnose root cause, or autonomously retry/compensate effects. Scheduler output is a plan. Runtime/replanning surfaces may provide observed evidence or perform separately authorized actions.

See scheduling methods and source scope and the existing source ledger.

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

同じリポジトリのスキル

概要と使いどころ

Expert in 2000s-era music visualization (Milkdrop, AVS, Geiss) and modern WebGL implementations. Specializes in Butterchurn integration, Web Audio API AnalyserNode FFT data, GLSL shaders for audio-reactive visuals, and psychedelic generative art. Activate on "Milkdrop", "music visualization", "WebGL visualizer", "Butterchurn", "audio reactive", "FFT visualization", "spectrum analyzer". NOT for simple bar charts/waveforms (use basic canvas), video editing, or non-audio visuals.

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

Expert legal research agent for finding and scraping expungement data state by state. Knows authoritative sources, URL patterns, Firecrawl configuration, and 2026 legal landscape.

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

Expert in 3D computer vision labeling tools, workflows, and AI-assisted annotation for LiDAR, point clouds, and sensor fusion. Covers SAM4D/Point-SAM, human-in-the-loop architectures, and vertical-specific training strategies. Activate on '3D labeling', 'point cloud annotation', 'LiDAR labeling', 'SAM 3D', 'SAM4D', 'sensor fusion annotation', '3D bounding box', 'semantic segmentation point cloud'. NOT for 2D image labeling (use clip-aware-embeddings), general ML training (use ml-engineer), video annotation without 3D (use computer-vision-pipeline), or VLM prompt engineering (use prompt-engineer).

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

Apply crisis decision-making research to agent routing, uncertainty triage, and coordination failure analysis in time-pressured systems. Use when diagnosing handoff failures, analytical paralysis, or expert judgment under incomplete information. NOT for routine coding, simple CRUD design, or static single-agent tasks with complete information.

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

Use for insight, reframing, contradiction, impasse, and anomaly-driven problem solving when execution effort no longer helps. NOT for routine optimization, error correction, or well-specified tasks with known solution paths.

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

Apply cognitive task analysis to expert work that depends on perceptual cues, branching judgment, and recurring monitoring loops. Use when decomposing expert capability into agent structure, simulation design, or validation interviews. NOT for ordinary step-by-step SOP capture or simple pipelines with no tacit cue layer.

日本語の概要は準備中です。原文の説明を表示しています。

curiositech/port-daddy22026年10月12日 更新

curiositech のスキルをすべて見る

このスキルの問題を報告する