Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.
日本語の概要は準備中です。原文の説明を表示しています。
Compress construction schedules using crashing and fast-tracking techniques. Analyze cost-time tradeoffs and find optimal acceleration strategies.
インストールする前に、エージェントに与えられる指示の中身を確認できます。
Compress construction schedules when project deadlines are at risk. Apply crashing (adding resources) and fast-tracking (parallel activities) to accelerate delivery while managing cost and risk.
"Strategic compression can recover 20% of schedule with 10% cost increase" — DDC Community
┌─────────────────────────────────────────────────────────────────┐
│ SCHEDULE COMPRESSION │
├─────────────────────────────────────────────────────────────────┤
│ │
│ CRASHING FAST-TRACKING │
│ ──────── ───────────── │
│ Add resources to reduce Overlap sequential │
│ activity duration activities │
│ │
│ Before: ████████ (10d) Before: A ──→ B ──→ C │
│ After: █████ (5d) + $$$ After: A ──→ B │
│ └──→ C │
│ Cost: Higher labor/OT Risk: Rework if A changes │
│ │
└─────────────────────────────────────────────────────────────────┘
from dataclasses import dataclass, field
from typing import List, Dict, Optional, Tuple
from enum import Enum
class CompressionMethod(Enum):
CRASH = "crash"
FAST_TRACK = "fast_track"
HYBRID = "hybrid"
@dataclass
class Activity:
id: str
name: str
normal_duration: int
crash_duration: int # Minimum possible duration
normal_cost: float
crash_cost: float # Cost at crash duration
predecessors: List[str] = field(default_factory=list)
is_critical: bool = False
current_duration: int = 0
def __post_init__(self):
if self.current_duration == 0:
self.current_duration = self.normal_duration
@property
def crash_slope(self) -> float:
"""Cost per day of crashing."""
duration_diff = self.normal_duration - self.crash_duration
if duration_diff == 0:
return float('inf')
return (self.crash_cost - self.normal_cost) / duration_diff
@property
def days_available_to_crash(self) -> int:
"""Days activity can still be crashed."""
return self.current_duration - self.crash_duration
@dataclass
class FastTrackOption:
activity1_id: str
activity2_id: str
overlap_days: int
risk_level: str # low, medium, high
risk_description: str
rework_probability: float
potential_rework_cost: float
@dataclass
class CompressionPlan:
target_reduction: int
achieved_reduction: int
crash_activities: List[Tuple[str, int]] # (activity_id, days_crashed)
fast_track_options: List[FastTrackOption]
total_additional_cost: float
new_project_duration: int
risk_assessment: str
class ScheduleCompressor:
"""Compress construction schedules using crashing and fast-tracking."""
def __init__(self):
self.activities: Dict[str, Activity] = {}
self.fast_track_options: List[FastTrackOption] = []
self.project_duration: int = 0
self.critical_path: List[str] = []
def add_activity(self, id: str, name: str,
normal_duration: int, crash_duration: int,
normal_cost: float, crash_cost: float,
predecessors: List[str] = None,
is_critical: bool = False) -> Activity:
"""Add activity with crash data."""
activity = Activity(
id=id,
name=name,
normal_duration=normal_duration,
crash_duration=crash_duration,
normal_cost=normal_cost,
crash_cost=crash_cost,
predecessors=predecessors or [],
is_critical=is_critical
)
self.activities[id] = activity
return activity
def add_fast_track_option(self, activity1_id: str, activity2_id: str,
overlap_days: int, risk_level: str,
risk_description: str,
rework_probability: float = 0.1,
potential_rework_cost: float = 0) -> FastTrackOption:
"""Add fast-tracking option between activities."""
option = FastTrackOption(
activity1_id=activity1_id,
activity2_id=activity2_id,
overlap_days=overlap_days,
risk_level=risk_level,
risk_description=risk_description,
rework_probability=rework_probability,
potential_rework_cost=potential_rework_cost
)
self.fast_track_options.append(option)
return option
def calculate_project_duration(self) -> int:
"""Calculate current project duration using CPM."""
# Simple forward pass
finish_times = {}
def get_finish(act_id: str) -> int:
if act_id in finish_times:
return finish_times[act_id]
act = self.activities[act_id]
if not act.predecessors:
start = 0
else:
start = max(get_finish(p) for p in act.predecessors)
finish_times[act_id] = start + act.current_duration
return finish_times[act_id]
for act_id in self.activities:
get_finish(act_id)
self.project_duration = max(finish_times.values()) if finish_times else 0
return self.project_duration
def identify_critical_path(self) -> List[str]:
"""Identify critical path activities."""
# Simplified - in practice, use full CPM
self.calculate_project_duration()
# Mark activities with zero float as critical
critical = [act.id for act in self.activities.values() if act.is_critical]
self.critical_path = critical
return critical
def analyze_crash_options(self) -> List[Dict]:
"""Analyze all crashing options sorted by cost efficiency."""
crash_options = []
for act in self.activities.values():
if act.days_available_to_crash > 0 and act.is_critical:
crash_options.append({
'activity_id': act.id,
'activity_name': act.name,
'crash_slope': act.crash_slope,
'max_days': act.days_available_to_crash,
'current_duration': act.current_duration,
'crash_duration': act.crash_duration
})
# Sort by crash slope (cost per day)
return sorted(crash_options, key=lambda x: x['crash_slope'])
def crash_schedule(self, target_days: int,
max_budget: float = float('inf')) -> CompressionPlan:
"""Crash schedule to reduce duration by target days."""
self.calculate_project_duration()
original_duration = self.project_duration
crashed_activities = []
total_cost = 0
days_achieved = 0
# Get crash options
options = self.analyze_crash_options()
while days_achieved < target_days and options:
# Find cheapest option
best_option = None
for opt in options:
if opt['max_days'] > 0:
best_option = opt
break
if not best_option:
break
# Crash by 1 day
act = self.activities[best_option['activity_id']]
crash_cost = act.crash_slope
if total_cost + crash_cost > max_budget:
break
act.current_duration -= 1
total_cost += crash_cost
days_achieved += 1
# Update option
best_option['max_days'] -= 1
# Track what was crashed
existing = next((c for c in crashed_activities if c[0] == act.id), None)
if existing:
crashed_activities.remove(existing)
crashed_activities.append((act.id, existing[1] + 1))
else:
crashed_activities.append((act.id, 1))
# Refresh options (critical path may change)
options = self.analyze_crash_options()
new_duration = self.calculate_project_duration()
return CompressionPlan(
target_reduction=target_days,
achieved_reduction=days_achieved,
crash_activities=crashed_activities,
fast_track_options=[],
total_additional_cost=total_cost,
new_project_duration=new_duration,
risk_assessment="Low risk - crashing uses proven methods"
)
def fast_track_schedule(self, target_days: int,
max_risk: str = "medium") -> CompressionPlan:
"""Fast-track schedule by overlapping activities."""
risk_order = {"low": 1, "medium": 2, "high": 3}
max_risk_level = risk_order.get(max_risk, 2)
# Filter options by risk level
viable_options = [
opt for opt in self.fast_track_options
if risk_order.get(opt.risk_level, 3) <= max_risk_level
]
# Sort by overlap (most time saved first)
viable_options.sort(key=lambda x: -x.overlap_days)
selected_options = []
total_overlap = 0
total_risk_cost = 0
for opt in viable_options:
if total_overlap >= target_days:
break
selected_options.append(opt)
total_overlap += opt.overlap_days
total_risk_cost += opt.rework_probability * opt.potential_rework_cost
self.calculate_project_duration()
new_duration = self.project_duration - total_overlap
risk_text = "High risk" if max_risk == "high" else "Moderate risk" if max_risk == "medium" else "Low risk"
return CompressionPlan(
target_reduction=target_days,
achieved_reduction=total_overlap,
crash_activities=[],
fast_track_options=selected_options,
total_additional_cost=total_risk_cost,
new_project_duration=new_duration,
risk_assessment=f"{risk_text} - potential rework if predecessor changes"
)
def optimize_compression(self, target_days: int,
max_budget: float,
max_risk: str = "medium") -> CompressionPlan:
"""Find optimal combination of crashing and fast-tracking."""
# Try crash-only
crash_plan = self.crash_schedule(target_days, max_budget)
if crash_plan.achieved_reduction >= target_days:
return crash_plan
# Need additional fast-tracking
remaining_days = target_days - crash_plan.achieved_reduction
remaining_budget = max_budget - crash_plan.total_additional_cost
fast_track_plan = self.fast_track_schedule(remaining_days, max_risk)
# Combine plans
total_reduction = crash_plan.achieved_reduction + fast_track_plan.achieved_reduction
total_cost = crash_plan.total_additional_cost + fast_track_plan.total_additional_cost
return CompressionPlan(
target_reduction=target_days,
achieved_reduction=total_reduction,
crash_activities=crash_plan.crash_activities,
fast_track_options=fast_track_plan.fast_track_options,
total_additional_cost=total_cost,
new_project_duration=self.project_duration - total_reduction,
risk_assessment="Combined approach - balance of cost and risk"
)
def generate_cost_curve(self, max_compression: int) -> List[Dict]:
"""Generate time-cost tradeoff curve."""
curve = []
self.calculate_project_duration()
original_duration = self.project_duration
# Reset all activities to normal
for act in self.activities.values():
act.current_duration = act.normal_duration
base_cost = sum(act.normal_cost for act in self.activities.values())
curve.append({
'duration': original_duration,
'cost': base_cost,
'compression': 0
})
for days in range(1, max_compression + 1):
# Reset and crash by 'days'
for act in self.activities.values():
act.current_duration = act.normal_duration
plan = self.crash_schedule(days)
if plan.achieved_reduction < days:
break
curve.append({
'duration': plan.new_project_duration,
'cost': base_cost + plan.total_additional_cost,
'compression': days
})
return curve
def generate_compression_report(self, plan: CompressionPlan) -> str:
"""Generate compression analysis report."""
lines = [
"# Schedule Compression Report",
"",
f"**Target Reduction:** {plan.target_reduction} days",
f"**Achieved Reduction:** {plan.achieved_reduction} days",
f"**New Duration:** {plan.new_project_duration} days",
f"**Additional Cost:** ${plan.total_additional_cost:,.0f}",
"",
f"## Risk Assessment",
f"{plan.risk_assessment}",
""
]
if plan.crash_activities:
lines.append("## Crashed Activities")
lines.append("")
lines.append("| Activity | Days Crashed | Cost Impact |")
lines.append("|----------|--------------|-------------|")
for act_id, days in plan.crash_activities:
act = self.activities[act_id]
cost = days * act.crash_slope
lines.append(f"| {act.name} | {days} | ${cost:,.0f} |")
lines.append("")
if plan.fast_track_options:
lines.append("## Fast-Tracked Activities")
lines.append("")
for opt in plan.fast_track_options:
lines.append(f"- **{opt.activity1_id} → {opt.activity2_id}**: {opt.overlap_days} days overlap")
lines.append(f" - Risk: {opt.risk_level} - {opt.risk_description}")
lines.append("")
return "\n".join(lines)
# Initialize compressor
compressor = ScheduleCompressor()
# Add activities with crash data
compressor.add_activity(
"A", "Foundation",
normal_duration=20, crash_duration=15,
normal_cost=100000, crash_cost=130000,
is_critical=True
)
compressor.add_activity(
"B", "Steel Erection",
normal_duration=30, crash_duration=22,
normal_cost=200000, crash_cost=260000,
predecessors=["A"],
is_critical=True
)
compressor.add_activity(
"C", "MEP Rough-in",
normal_duration=25, crash_duration=20,
normal_cost=150000, crash_cost=180000,
predecessors=["B"],
is_critical=True
)
# Add fast-track options
compressor.add_fast_track_option(
"A", "B", overlap_days=5,
risk_level="medium",
risk_description="Steel may need rework if foundation changes",
rework_probability=0.15,
potential_rework_cost=30000
)
# Analyze crash options
print("Crash Options (sorted by cost/day):")
for opt in compressor.analyze_crash_options():
print(f" {opt['activity_name']}: ${opt['crash_slope']:.0f}/day, max {opt['max_days']} days")
# Compress schedule by 15 days
plan = compressor.optimize_compression(
target_days=15,
max_budget=80000,
max_risk="medium"
)
print(compressor.generate_compression_report(plan))
# Generate cost curve
curve = compressor.generate_cost_curve(20)
for point in curve:
print(f"Duration: {point['duration']}d, Cost: ${point['cost']:,.0f}")
pip install (no external dependencies)
まだレビューはありません。使ってみた感想をお寄せください。
概要と使いどころ
Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.
日本語の概要は準備中です。原文の説明を表示しています。
Analyze 5000+ IFC and Revit projects at scale for patterns, benchmarks, and insights. Big data analysis for construction.
日本語の概要は準備中です。原文の説明を表示しています。
Check construction AI systems against the EU AI Act (Regulation 2024/1689): classify risk of estimation, scheduling, CV and agent tools, document transparency, keep human oversight. Use when deploying or auditing AI in construction.
日本語の概要は準備中です。原文の説明を表示しています。
Orchestrate multiple AI agents for construction workflows: estimator, scheduler, document, QA and safety agents coordinated by a supervisor agent, with human checkpoints. Use when automating end-to-end project processes with agentic AI.
日本語の概要は準備中です。原文の説明を表示しています。
Create Apache Airflow DAGs for construction data pipelines. Orchestrate ETL, validation, and reporting workflows.
日本語の概要は準備中です。原文の説明を表示しています。
Automate as-built documentation and digital handover for construction. Compile project records, generate O&M manuals, create asset databases, and ensure complete project closeout.
日本語の概要は準備中です。原文の説明を表示しています。