Analyze weather impact on construction schedule. Predict delays and adjust activities based on forecast.
インストールする前に、エージェントに与えられる指示の中身を確認できます。
import pandas as pd
from datetime import date, timedelta
from typing import Dict, Any, List, Optional
from dataclasses import dataclass, field
from enum import Enum
class WeatherCondition(Enum):
CLEAR = "clear"
CLOUDY = "cloudy"
RAIN = "rain"
HEAVY_RAIN = "heavy_rain"
SNOW = "snow"
WIND = "wind"
EXTREME_HEAT = "extreme_heat"
EXTREME_COLD = "extreme_cold"
class ActivitySensitivity(Enum):
HIGH = "high" # Concrete, painting, roofing
MEDIUM = "medium" # Excavation, masonry
LOW = "low" # Indoor work
@dataclass
class WeatherForecast:
forecast_date: date
condition: WeatherCondition
high_temp: float
low_temp: float
precipitation_mm: float
wind_speed_kmh: float
@dataclass
class ScheduleActivity:
activity_id: str
name: str
start_date: date
end_date: date
sensitivity: ActivitySensitivity
outdoor: bool
can_work_in_rain: bool = False
min_temp: float = 5.0
max_temp: float = 35.0
max_wind: float = 50.0
@dataclass
class WeatherImpact:
activity_id: str
impact_date: date
reason: str
delay_hours: float
recommendation: str
class WeatherImpactScheduler:
def __init__(self, project_name: str):
self.project_name = project_name
self.activities: Dict[str, ScheduleActivity] = {}
self.forecasts: Dict[date, WeatherForecast] = {}
self.impacts: List[WeatherImpact] = []
def add_activity(self, activity_id: str, name: str, start_date: date,
end_date: date, sensitivity: ActivitySensitivity,
outdoor: bool = True, can_work_in_rain: bool = False) -> ScheduleActivity:
activity = ScheduleActivity(
activity_id=activity_id,
name=name,
start_date=start_date,
end_date=end_date,
sensitivity=sensitivity,
outdoor=outdoor,
can_work_in_rain=can_work_in_rain
)
self.activities[activity_id] = activity
return activity
def add_forecast(self, forecast_date: date, condition: WeatherCondition,
high_temp: float, low_temp: float,
precipitation_mm: float = 0, wind_speed_kmh: float = 0):
forecast = WeatherForecast(
forecast_date=forecast_date,
condition=condition,
high_temp=high_temp,
low_temp=low_temp,
precipitation_mm=precipitation_mm,
wind_speed_kmh=wind_speed_kmh
)
self.forecasts[forecast_date] = forecast
def analyze_impacts(self) -> List[WeatherImpact]:
self.impacts = []
for activity in self.activities.values():
if not activity.outdoor:
continue
current = activity.start_date
while current <= activity.end_date:
forecast = self.forecasts.get(current)
if forecast:
impact = self._check_impact(activity, forecast)
if impact:
self.impacts.append(impact)
current += timedelta(days=1)
return self.impacts
def _check_impact(self, activity: ScheduleActivity,
forecast: WeatherForecast) -> Optional[WeatherImpact]:
reasons = []
delay_hours = 0
# Check precipitation
if forecast.condition in [WeatherCondition.RAIN, WeatherCondition.HEAVY_RAIN]:
if not activity.can_work_in_rain:
if activity.sensitivity == ActivitySensitivity.HIGH:
reasons.append("Rain - high sensitivity activity")
delay_hours = 8
else:
reasons.append("Rain delays")
delay_hours = 4
# Check temperature
if forecast.low_temp < activity.min_temp:
reasons.append(f"Too cold ({forecast.low_temp}°C)")
delay_hours = max(delay_hours, 8 if activity.sensitivity == ActivitySensitivity.HIGH else 4)
if forecast.high_temp > activity.max_temp:
reasons.append(f"Too hot ({forecast.high_temp}°C)")
delay_hours = max(delay_hours, 4)
# Check wind
if forecast.wind_speed_kmh > activity.max_wind:
reasons.append(f"High wind ({forecast.wind_speed_kmh} km/h)")
delay_hours = max(delay_hours, 8)
if reasons:
return WeatherImpact(
activity_id=activity.activity_id,
impact_date=forecast.forecast_date,
reason="; ".join(reasons),
delay_hours=delay_hours,
recommendation=self._get_recommendation(activity, forecast)
)
return None
def _get_recommendation(self, activity: ScheduleActivity,
forecast: WeatherForecast) -> str:
if forecast.condition in [WeatherCondition.RAIN, WeatherCondition.HEAVY_RAIN]:
return "Reschedule or plan indoor work"
if forecast.low_temp < activity.min_temp:
return "Use heating blankets or delay start"
if forecast.high_temp > activity.max_temp:
return "Start early, plan heat breaks"
if forecast.wind_speed_kmh > activity.max_wind:
return "Secure materials, delay crane work"
return "Monitor conditions"
def get_total_delay_forecast(self) -> Dict[str, Any]:
total_hours = sum(i.delay_hours for i in self.impacts)
by_activity = {}
for impact in self.impacts:
act = impact.activity_id
by_activity[act] = by_activity.get(act, 0) + impact.delay_hours
return {
'total_impact_hours': total_hours,
'total_impact_days': round(total_hours / 8, 1),
'affected_activities': len(by_activity),
'by_activity': by_activity,
'impact_count': len(self.impacts)
}
def export_analysis(self, output_path: str):
data = [{
'Activity': i.activity_id,
'Date': i.impact_date,
'Reason': i.reason,
'Delay Hours': i.delay_hours,
'Recommendation': i.recommendation
} for i in self.impacts]
pd.DataFrame(data).to_excel(output_path, index=False)
scheduler = WeatherImpactScheduler("Office Tower")
# Add activities
scheduler.add_activity("CONC-001", "Pour Slab L3", date(2024, 3, 15),
date(2024, 3, 20), ActivitySensitivity.HIGH, outdoor=True)
# Add forecasts
scheduler.add_forecast(date(2024, 3, 17), WeatherCondition.RAIN, 15, 8, 25, 20)
# Analyze
impacts = scheduler.analyze_impacts()
summary = scheduler.get_total_delay_forecast()
print(f"Projected delay: {summary['total_impact_days']} days")
まだレビューはありません。使ってみた感想をお寄せください。
概要と使いどころ
Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.
日本語の概要は準備中です。原文の説明を表示しています。
Analyze 5000+ IFC and Revit projects at scale for patterns, benchmarks, and insights. Big data analysis for construction.
日本語の概要は準備中です。原文の説明を表示しています。
Check construction AI systems against the EU AI Act (Regulation 2024/1689): classify risk of estimation, scheduling, CV and agent tools, document transparency, keep human oversight. Use when deploying or auditing AI in construction.
日本語の概要は準備中です。原文の説明を表示しています。
Orchestrate multiple AI agents for construction workflows: estimator, scheduler, document, QA and safety agents coordinated by a supervisor agent, with human checkpoints. Use when automating end-to-end project processes with agentic AI.
日本語の概要は準備中です。原文の説明を表示しています。
Create Apache Airflow DAGs for construction data pipelines. Orchestrate ETL, validation, and reporting workflows.
日本語の概要は準備中です。原文の説明を表示しています。
Automate as-built documentation and digital handover for construction. Compile project records, generate O&M manuals, create asset databases, and ensure complete project closeout.
日本語の概要は準備中です。原文の説明を表示しています。