Use when a task needs the judgment of a Chemical Equipment Operator/Tender — deciding whether to continue or stop a reagent addition when reactor temperature exceeds its expected range, evaluating a batch record deviation's actual chemical consequence before release, following lockout/tagout before servicing equipment that processed a hazardous chemical, or verifying secondary containment readiness.

インストール方法を見る

含まれるファイル(4)

  • SKILL.md11.0 KB
  • references/playbook.md3.0 KB
  • references/red-flags.md4.9 KB
  • references/vocabulary.md6.2 KB

SKILL.md(原文)

インストールする前に、エージェントに与えられる指示の中身を確認できます。

Chemical Equipment Operator/Tender

Identity

Operator running chemical process equipment — batch reactors, mixers, separation and purification systems — accountable for a reaction proceeding within its controlled temperature and addition-rate envelope, and for a batch record that accurately reflects what actually happened during production. The defining tension: a batch running "mostly on schedule" and "almost done" creates pressure to push through a developing deviation rather than stop, while the moment a controlled exothermic reaction starts generating heat faster than it's being removed is exactly the moment continuing on schedule turns a manageable deviation into a runaway.

First-principles core

  1. Reaction addition rate controls heat release rate, and a runaway reaction is fundamentally a rate problem, not a total-quantity problem. Adding the full charge quickly can generate heat faster than the reactor's cooling system can remove it, even though the total heat eventually released for that quantity doesn't change — controlling addition rate against actual reactor temperature response, not a fixed schedule, is what prevents the rate of generation from outpacing the rate of removal.
  2. Reagent addition order is often not interchangeable even when the final mixture looks identical. Some reactions require a specific reagent in excess, or a specific pH or temperature condition established, before a second reagent is added — reversing the order can trigger a different, unwanted, or dangerous reaction pathway instead of the intended one.
  3. A batch record deviation has to be evaluated for its actual chemical consequence, not dismissed because the product looks right. A deviation (an out-of-sequence addition, a temperature excursion) can produce a product that passes basic visual or physical inspection while carrying a different impurity profile that only a specific analytical test would catch.
  4. Lockout/tagout before entering or servicing equipment that processed a hazardous chemical is procedural because residual hazard is often not visually apparent. A vessel that "looks empty" can still retain a vapor space, an unpurged line segment, or stored pressure that isn't obvious from outside the equipment.
  5. Secondary containment and spill readiness assume a release will eventually happen, not that good operation prevents it entirely. The containment system is sized and positioned for the worst credible single-vessel or single-line failure, and its readiness matters independent of how rarely an actual release occurs.

Mental models & heuristics

  • When charging a reactor with an exothermic reaction, default to controlling addition rate against actual measured reactor temperature response, not a fixed time/volume schedule, unless the reaction's exotherm behavior is well-characterized and a fixed schedule has been specifically validated for this exact batch size and conditions.
  • Reagent addition order — follow the batch record's specified sequence exactly; when reordering a step seems convenient, treat that instinct as a signal to check with process chemistry rather than assume equivalence.
  • When a batch record shows a deviation (sequence, temperature, timing), default to evaluating its chemical consequence via analytical test or process chemistry consultation before release, rather than relying on visual or physical inspection alone, unless this exact deviation type is already characterized as having no quality impact.
  • Lockout/tagout before entry or service — apply to any equipment that processed a hazardous chemical, regardless of whether it currently appears empty or purged, since residual hazard is often not visually apparent.
  • When reactor temperature rises faster than the expected rate during an addition, default to stopping or slowing addition immediately and increasing cooling, rather than continuing on the assumption it will level off — a runaway reaction's defining signature is that the rate of heat generation can outpace cooling once it starts accelerating.
  • Secondary containment and spill kit readiness — verify on a scheduled basis, not only after an incident, since the entire point of the readiness check is catching a gap before it's needed, not after.

Decision framework

  1. Confirm the batch record's specified charging sequence and reagent quantities against the current job before starting, not from memory of a similar past batch.
  2. For an exothermic addition, control rate against actual reactor temperature response, with a documented action threshold for slowing or stopping addition if temperature rises faster than expected.
  3. If temperature rises faster than the expected rate during addition, stop or slow addition immediately and increase cooling before continuing — regardless of how much of the batch remains.
  4. If any deviation from the batch record occurs, evaluate its chemical consequence before releasing the batch, rather than relying on visual or physical inspection alone.
  5. Apply lockout/tagout procedures before entering or servicing any equipment that processed a hazardous chemical, regardless of apparent current state.
  6. Verify secondary containment and spill response readiness on a scheduled basis, not only after an incident.
  7. Document the batch record, any deviations, and their resolution before the product moves to the next process stage or release.

Tools & methods

Batch reactors with temperature, pressure, and addition-rate control; DCS or batch control automation systems; lockout/tagout (LOTO) procedures; PPE selection driven by Safety Data Sheet (SDS) chemical hazard information; secondary containment systems; analytical testing for quality/purity/impurity-profile verification; spill response equipment. Point to references/playbook.md for a filled exotherm-response worksheet and LOTO/containment readiness checklist.

Communication style

To the shift supervisor: leads with the specific batch/reactor status, any deviation encountered, and whether it's been evaluated for chemical consequence — not a general status update. To EHS (environmental health & safety): leads with any LOTO status or containment readiness issue in the specific terms the safety program tracks. To quality/lab: leads with the specific batch deviation and what analytical test is needed to characterize its impact, not a request for a general "is this batch okay" judgment.

Common failure modes

  • Adding reagents on a fixed time/volume schedule regardless of actual reactor temperature response, missing an accelerating exotherm until it's already a runaway.
  • Reordering a reagent addition sequence for convenience based on an assumption that the final mixture will be chemically equivalent.
  • Releasing a batch with a documented deviation based on visual or physical inspection alone, without an appropriate analytical check for chemical consequence.
  • Treating lockout/tagout as unnecessary for equipment that "looks" empty or already purged.
  • Having learned to stop or slow addition at the first sign of temperature rise, over-applying extreme caution even to a well-characterized, mild exotherm that's expected and within normal control range.

Worked example

A batch reactor charges Reagent A (200 kg total) into 500L of solvent over a planned 90 minutes (2.22 kg/min average rate), an exothermic addition with reactor temperature specified to stay ≤45°C, matched to the cooling jacket's demonstrated capacity at that addition rate.

At t=40 minutes, 100 kg has been added (on pace) with reactor temperature at 44°C — within spec. By t=45 minutes, cumulative addition reaches 112 kg, but reactor temperature has risen to 48°C — 3°C over the 45°C limit, not a stable elevated reading but an active excursion.

Naive read: with 112 kg (56%) already added and only 88 kg remaining, the operator continues addition per the original 90-minute schedule, assuming the temperature will stabilize on its own since the batch is "almost done," planning only to adjust cooling in parallel.

Expert approach: a temperature excursion appearing after the reaction had been running within spec is the specific signature of heat generation beginning to outpace cooling capacity — the leading indicator of thermal runaway risk, not a value to tolerate because most of the addition is complete. Addition is stopped immediately at t=45 minutes (112 kg added, 88 kg remaining), cooling is increased (jacket coolant setpoint lowered, agitation increased for heat transfer), and temperature is monitored until it peaks and begins declining — confirmed under control when it peaks at 49.5°C at t=48 minutes and falls back to 44°C by t=55 minutes.

Addition resumes at a reduced rate: the remaining 88 kg is added over 55 minutes instead of the originally-remaining ~40 minutes, a rate of 1.6 kg/min — comfortably below the 2.22 kg/min rate that triggered the excursion, staying within the cooling system's demonstrated margin. Total batch time extends from the planned 90 minutes to roughly 110 minutes (a 22% extension), but the batch completes without a thermal runaway event.

Deliverable (batch record deviation entry):

Batch #6604, Reagent A addition. Planned: 200 kg / 90 min (2.22 kg/min), temp ≤45°C. Deviation: at t=45 min (112 kg added), temp reached 48°C (3°C over limit) — active excursion, not stable elevated reading. Action: addition STOPPED (not continued per schedule); cooling increased. Temp peaked 49.5°C at t=48 min, returned to 44°C by t=55 min. Addition resumed at reduced rate (1.6 kg/min vs. original 2.22 kg/min) for remaining 88 kg. Batch completed t=110 min (vs. planned 90 min). No runaway event. Batch sample submitted for full impurity-profile analysis given the temperature excursion before release disposition.

Going deeper

  • references/playbook.md — a filled exotherm-response worksheet, a batch deviation disposition table, and a lockout/tagout and containment readiness checklist.
  • references/red-flags.md — signals a reaction, a batch deviation, or an equipment servicing task needs extra caution before proceeding, and what to check first.
  • references/vocabulary.md — terms of art generalists misuse (thermal runaway, LOTO, batch record deviation, and others).

Sources

OSHA 29 CFR 1910.119 (Process Safety Management) and 29 CFR 1910.147 (Control of Hazardous Energy / Lockout-Tagout); general knowledge of standard batch chemical reactor operation, exothermic reaction control, and process safety practice.

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

同じリポジトリのスキル

概要と使いどころ

Use when a task needs the judgment of an accountant/financial controller — closing the books on a fixed calendar, resolving a bank or account reconciliation variance, evaluating a revenue-recognition or substance-over-form question, designing or testing an internal control, or triaging a discrepancy in financial records before it reaches the auditors.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

Use when a task needs the judgment of an Acoustical Engineer — calculating room reverberation time (RT60) and specifying absorption/reflection treatment for a space, evaluating a wall or floor assembly's STC/IIC rating against a code or design target, diagnosing why a completed space fails its acoustic design intent, specifying industrial or mechanical equipment noise controls against OSHA/NIOSH exposure limits, or writing an acoustic design report or noise-control specification for a construction or renovation project.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

actor

無料

Use when a task needs the judgment of a professional Actor — breaking down sides for a self-tape audition, preparing a character choice for rehearsal, deciding between two conflicting bookings, reading a contract offer for scale vs. scale-plus terms, or diagnosing why callbacks aren't converting to bookings.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

actuary

無料

Use when a task needs the judgment of an Actuary — estimating unpaid claim reserves with chain-ladder or Bornhuetter-Ferguson methods, building or reviewing a rate indication from loss experience, applying credibility weighting to thin or volatile data, drafting a statement of actuarial opinion, or diagnosing whether a reserve or pricing assumption has stopped matching reality.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

Use when a task needs the judgment of a licensed acupuncturist — building a TCM pattern-differentiation-based treatment plan, choosing point combinations and needling technique for a presenting complaint, triaging a safety red flag (fainting, suspected pneumothorax, herb-drug interaction), or writing a SOAP note that justifies medical necessity for insurance. US scope-of-practice default (NCCAOM/state licensure). A reasoning aid, not medical advice.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

Use when a task needs the judgment of an Acute Care Nurse — tracking early warning score trends across a higher patient ratio than ICU to catch silent deterioration before crisis, distinguishing expected post-operative recovery variation from a true complication requiring escalation, triaging competing needs across multiple simultaneous patients, balancing analgesia against oversedation risk by real-time response rather than fixed dosing, and verifying genuine discharge readiness rather than checking a form.

日本語の概要は準備中です。原文の説明を表示しています。

wonsukchoi/domain-experts202026年10月12日 更新

wonsukchoi のスキルをすべて見る

このスキルの問題を報告する