Plan database migrations before executing them: risk assessment, dependency mapping, multi-service sequencing, rollback budgets, and stakeholder communication plans. Use when deciding HOW to migrate, not when writing the actual DDL. NOT for: writing migration SQL (use database-migration-manager), data ETL pipelines (use data-migration-specialist), query optimization, or ORM configuration.

中文简介正在准备中。当前显示原文说明。

集成工具PostgreSQLMySQL
查看安装方法

包含的文件(1)

  • SKILL.md8.6 KB

SKILL.md(原文)

安装前可以查看交给 AI 代理的指令内容。

Database Migration Planner

Plans safe, sequenced database migrations before any SQL is written. Produces migration plans with risk scores, dependency graphs, rollback budgets, and communication timelines.

When to Use

✅ Use for: Deciding migration strategy, risk-scoring schema changes, sequencing migrations across multiple services, estimating rollback windows, planning communication to dependent teams, assessing lock contention risk, choosing between expand-contract vs. blue-green vs. big-bang.

❌ NOT for: Writing DDL/migration files (→ database-migration-manager), executing data pipelines (→ data-migration-specialist), query performance (→ postgresql-optimization), ORM config (→ drizzle-migrations).

Core Process

flowchart TD
  A[Describe the change] --> B{Single service?}
  B -->|Yes| C[Assess risk level]
  B -->|No| D[Map service dependencies]
  D --> E[Determine migration order]
  E --> C
  C --> F{Risk level}
  F -->|Low: additive only| G[Direct migration plan]
  F -->|Medium: modify existing| H[Expand-contract plan]
  F -->|High: destructive or cross-service| I[Phased rollout plan]
  G --> J[Estimate rollback budget]
  H --> J
  I --> J
  J --> K[Communication plan]
  K --> L[Final migration plan document]

Risk Classification

Risk LevelCharacteristicsStrategyRollback Budget
LowAdditive only (new table, new nullable column, new index on small table)Direct applyMinutes
MediumModifies existing (column type change, NOT NULL addition, index on large table)Expand-contractHours
HighDestructive (drop column/table, rename across services, data type narrowing)Phased rollout with feature flagsDays
CriticalCross-database, multi-region, or involves PII restructuringBlue-green database with traffic replayWeeks

Decision Trees

Strategy Selection

flowchart TD
  Q1{Can old code work with new schema?}
  Q1 -->|Yes| Q2{Is the change additive?}
  Q1 -->|No| EXPAND[Expand-Contract required]
  Q2 -->|Yes| DIRECT[Direct migration]
  Q2 -->|No| Q3{Table size > 1M rows?}
  Q3 -->|Yes| ONLINE[Online DDL tool required]
  Q3 -->|No| EXPAND
  EXPAND --> Q4{Multiple services read this table?}
  Q4 -->|Yes| PHASED[Phased: migrate consumers first]
  Q4 -->|No| SINGLE[Single expand-contract cycle]

Lock Contention Assessment

flowchart TD
  L1{Operation type?}
  L1 -->|ADD COLUMN nullable| SAFE[No lock concern]
  L1 -->|ADD COLUMN NOT NULL + default| PG{Postgres ≥ 11?}
  PG -->|Yes| SAFE
  PG -->|No| REWRITE[Full table rewrite - dangerous]
  L1 -->|ALTER TYPE| REWRITE
  L1 -->|CREATE INDEX| CONC{Use CONCURRENTLY?}
  CONC -->|Yes| SAFE
  CONC -->|No| BLOCKS[Blocks writes for duration]
  L1 -->|DROP COLUMN| SAFE2[Instant in PG, rewrite in MySQL < 8.0]
  L1 -->|RENAME| INSTANT[Instant but breaks queries]

Anti-Patterns

Planning by DDL Complexity

Novice: "It's just one ALTER TABLE, ship it directly." Expert: Risk comes from service coupling and table size, not DDL line count. A single ALTER TABLE ADD COLUMN NOT NULL on a 500M-row table with 12 consuming services is Critical-risk regardless of its syntactic simplicity. Detection: Plan mentions "simple change" without noting row count or consumer count.

Rollback as Afterthought

Novice: "We'll figure out rollback if something goes wrong." Expert: Rollback is designed first. Every migration plan starts with: "How do I undo this in under X minutes?" If the answer is "you can't," the migration needs a different strategy (expand-contract, blue-green). Timeline: Pre-2020: rollback was optional for many teams. Post-incident-culture (2020+): rollback budget is a hard requirement.

Ignoring Read Replicas and Caches

Novice: Plans migration for primary only. Expert: Read replicas lag. Caches have stale schemas. A migration plan must account for: replica lag window, cache TTL expiry, connection pool recycling, and ORM schema cache invalidation. Miss any one and you get 500s from readers even though the primary migrated cleanly.

Migration Plan Template

When producing a plan, output this structure:

# Migration Plan: [Name]

## Summary
- **Change**: [What's changing]
- **Risk Level**: Low / Medium / High / Critical
- **Estimated Duration**: [Time from start to verified-complete]
- **Rollback Budget**: [Max time to fully reverse]
- **Affected Services**: [List]

## Dependencies
- [ ] Service A must deploy read-compatibility code first
- [ ] Cache TTL must expire (12h) before dropping old column
- [ ] Feature flag `new_schema_v2` must be enabled in staging first

## Sequence
| Step | Action | Duration | Rollback |
|------|--------|----------|----------|
| 1 | Deploy app code that reads both old+new | 30m | Revert deploy |
| 2 | Run forward migration | 5m | Run rollback SQL |
| 3 | Backfill new column from old | 2h | Truncate new column |
| 4 | Verify data integrity | 30m | N/A |
| 5 | Switch reads to new column | 15m | Feature flag off |
| 6 | Remove old column (after bake period) | 1 week | N/A (point of no return) |

## Rollback Plan
- **Trigger**: Error rate > 1% OR p99 latency > 2x baseline
- **Procedure**: [Specific steps]
- **Point of no return**: Step 6 (old column dropped)

## Communication
- [ ] Notify dependent teams 1 week before
- [ ] Post in #migrations channel day-of
- [ ] Update API docs if schema is exposed

Multi-Service Sequencing

When a migration spans multiple services:

  1. Map the dependency graph — Which services read/write the affected tables?
  2. Identify the critical path — Which service must migrate first (usually the writer)?
  3. Design compatibility windows — Period where both old and new schemas are valid
  4. Plan the rollout order:
    • Writers deploy dual-write code
    • Run schema migration (expand phase)
    • Readers deploy new-schema code
    • Verify all services healthy
    • Remove old-schema code (contract phase)
    • Drop old columns (after bake period)
sequenceDiagram
  participant Writer as Service A (Writer)
  participant DB as Database
  participant Reader1 as Service B (Reader)
  participant Reader2 as Service C (Reader)

  Note over Writer,Reader2: Phase 1: Expand
  Writer->>Writer: Deploy dual-write code
  Writer->>DB: ALTER TABLE ADD new_column
  Writer->>DB: Backfill new_column FROM old_column

  Note over Writer,Reader2: Phase 2: Migrate Readers
  Reader1->>Reader1: Deploy: read from new_column
  Reader2->>Reader2: Deploy: read from new_column

  Note over Writer,Reader2: Phase 3: Contract (after bake)
  Writer->>Writer: Remove old_column writes
  Writer->>DB: ALTER TABLE DROP old_column

Estimation Heuristics

FactorImpact on Duration
Table rows > 10M+1h per 100M rows for backfill
Consuming services > 3+1 week bake time per additional service
PII/compliance columns+1 week for legal review
Multi-region database2x total duration (replica sync)
No staging environment3x risk score (can't rehearse)
Active on-call incidentSTOP. Do not plan migrations during incidents.

References

  • references/risk-matrix.md — Detailed risk scoring with weighted factors for table size, consumer count, data sensitivity, and region topology
  • references/communication-templates.md — Pre-written Slack/email templates for migration announcements, go/no-go decisions, and incident escalation
  • references/platform-quirks.md — Database-specific gotchas: Postgres online DDL limitations, MySQL metadata locks, CockroachDB schema change jobs, PlanetScale branching model

评价

还没有评价。欢迎分享你的使用感受。

评论

无需登录即可发表。欢迎分享使用感受、提问,或说明在哪些环境下无法运行。

还没有评论。来写第一条吧。

提交后会立即公开。请勿填写邮箱、电话等个人信息。URL 最多 2 个。

0 / 1000 字

此表单受 reCAPTCHA 保护,适用 Google 的隐私权政策和服务条款。

同一仓库的技能

Expert in 2000s-era music visualization (Milkdrop, AVS, Geiss) and modern WebGL implementations. Specializes in Butterchurn integration, Web Audio API AnalyserNode FFT data, GLSL shaders for audio-reactive visuals, and psychedelic generative art. Activate on "Milkdrop", "music visualization", "WebGL visualizer", "Butterchurn", "audio reactive", "FFT visualization", "spectrum analyzer". NOT for simple bar charts/waveforms (use basic canvas), video editing, or non-audio visuals.

中文简介正在准备中。当前显示原文说明。

curiositech/port-daddy32026年10月18日 更新

Expert legal research agent for finding and scraping expungement data state by state. Knows authoritative sources, URL patterns, Firecrawl configuration, and 2026 legal landscape.

中文简介正在准备中。当前显示原文说明。

curiositech/port-daddy32026年10月18日 更新

Expert in 3D computer vision labeling tools, workflows, and AI-assisted annotation for LiDAR, point clouds, and sensor fusion. Covers SAM4D/Point-SAM, human-in-the-loop architectures, and vertical-specific training strategies. Activate on '3D labeling', 'point cloud annotation', 'LiDAR labeling', 'SAM 3D', 'SAM4D', 'sensor fusion annotation', '3D bounding box', 'semantic segmentation point cloud'. NOT for 2D image labeling (use clip-aware-embeddings), general ML training (use ml-engineer), video annotation without 3D (use computer-vision-pipeline), or VLM prompt engineering (use prompt-engineer).

中文简介正在准备中。当前显示原文说明。

curiositech/port-daddy32026年10月18日 更新

Apply crisis decision-making research to agent routing, uncertainty triage, and coordination failure analysis in time-pressured systems. Use when diagnosing handoff failures, analytical paralysis, or expert judgment under incomplete information. NOT for routine coding, simple CRUD design, or static single-agent tasks with complete information.

中文简介正在准备中。当前显示原文说明。

curiositech/port-daddy32026年10月18日 更新

Use for insight, reframing, contradiction, impasse, and anomaly-driven problem solving when execution effort no longer helps. NOT for routine optimization, error correction, or well-specified tasks with known solution paths.

中文简介正在准备中。当前显示原文说明。

curiositech/port-daddy32026年10月18日 更新

Apply cognitive task analysis to expert work that depends on perceptual cues, branching judgment, and recurring monitoring loops. Use when decomposing expert capability into agent structure, simulation design, or validation interviews. NOT for ordinary step-by-step SOP capture or simple pipelines with no tacit cue layer.