Fix Monte Carlo project completion simulations that give identical dates for all sub-groups (milestones, priorities, epics). Use when: (1) All sub-group predictions converge to the same date despite different remaining counts, (2) Proportional throughput scaling produces flat/identical results, (3) Applying overall scope rate to individual sub-groups causes simulations to hit max_weeks cap and never converge, (4) Building project forecasting tools that predict completion for sub-groups of a larger backlog. Covers hypergeometric draw model for milestones and cumulative priority model for sequential priorities.

中文简介正在准备中。当前显示原文说明。

查看安装方法

包含的文件(1)

  • SKILL.md5.9 KB

SKILL.md(原文)

安装前可以查看交给 AI 代理的指令内容。

Monte Carlo Sub-Group Prediction Scaling

Problem

When running Monte Carlo simulations for project completion, predicting dates for sub-groups (milestones, priorities, epics) within a larger project produces identical results for all groups, or simulations diverge and hit the max_weeks cap.

Context / Trigger Conditions

  • Building a project forecasting tool that predicts dates for individual milestones or priority groups within a larger project backlog
  • All sub-group predictions show the same date despite very different remaining counts (e.g., 5-item milestone shows same date as 46-item milestone)
  • Simulations hit max_weeks (104) and produce dates 2+ years in the future
  • Scope rate applied per-group causes negative net velocity (items grow each week)

Root Causes

1. Proportional Scaling is Mathematically Constant

If you scale throughput proportionally:

share = remaining_i / total_remaining
scaled_throughput = overall_throughput * share
weeks = remaining_i / scaled_throughput
      = remaining_i / (overall_throughput * remaining_i / total_remaining)
      = total_remaining / overall_throughput  # CONSTANT for all groups!

Every sub-group predicts the same number of weeks regardless of size.

2. Overall Scope Rate Overwhelms Sub-Group Throughput

If the project's overall scope rate is 50 items/week and you apply it to a sub-group with only 5 remaining items (share = 1.6%), the scaled throughput might be ~0.6/week while scaled scope is ~0.8/week. Net velocity is negative — the simulation never converges and hits max_weeks.

3. GitHub created_at ≠ "Added to Board"

Scope rate calculated from created_at dates reflects when GitHub issues were created, not when they were added to the project board. Bulk triaging or importing old issues inflates the apparent scope rate dramatically.

Solution

Use different simulation models for different sub-group types:

For Sequential Priorities (P0, P1, P2...): Cumulative Model

Higher priorities are completed first. Each priority's prediction includes all higher-priority work that must finish before it:

sorted_priorities = sorted(priorities, key=lambda p: p["name"])
cumulative_before = 0

for p in sorted_priorities:
    effective_remaining = cumulative_before + p["remaining"]
    result = simulate(
        remaining=effective_remaining,
        throughput_history=full_project_throughput,  # NOT scaled
        scope_rate=0.0,  # Don't apply scope per-group
    )
    result.remaining = p["remaining"]  # Show actual remaining
    cumulative_before += p["remaining"]

For Milestones/Epics: Hypergeometric Draw Model

Items from each milestone are randomly drawn from the overall work pool. Smaller milestones finish earlier due to higher variance:

for i in range(n_simulations):
    subset_left = remaining
    pool_left = total_remaining
    weeks = 0
    while subset_left > 0 and weeks < max_weeks:
        throughput = rng.choice(throughput_samples)
        draw_size = min(throughput, pool_left)
        if draw_size > 0 and pool_left > 0:
            other = pool_left - subset_left
            # How many completed items come from this milestone?
            drawn = rng.hypergeometric(subset_left, max(other, 0), draw_size)
            subset_left -= drawn
            pool_left -= draw_size
            pool_left = max(pool_left, subset_left)
        weeks += 1

Key Principles

  1. Don't scale throughput proportionally — it produces identical results
  2. Don't apply overall scope rate to sub-groups — it causes divergence
  3. Use the full project throughput for priority predictions (cumulative model)
  4. Use hypergeometric sampling for milestone predictions (discrete draws)
  5. Show scope rate as informational rather than baking it into per-group MC

Verification

  • Sub-groups with fewer remaining items should predict earlier dates
  • Smaller sub-groups should have wider confidence intervals (more variance)
  • No predictions should hit the max_weeks cap under normal conditions
  • Priority predictions should be ordered (P0 < P1 < P2 < P3)

Example

With throughput of [2, 29, 44, 34, 11, 24, 33, 54, 34, 101, 57, 81, 0] and 303 total remaining items:

Before fix (proportional scaling):

MVP Rel 1 (5 left):   Apr 13    # All identical!
MVP Rel 2 (46 left):  Apr 13
Release 3 (33 left):  Apr 13

After fix (hypergeometric draws):

MVP Rel 1 (5 left):   Apr 6     # Differentiated by size
MVP Rel 2 (46 left):  Apr 13
Release 3 (33 left):  Apr 13
Zap Store (10 left):  Apr 13

Notes

  • The continuous proportional model (subset_throughput = throughput * share) is mathematically equivalent to "everything finishes when the project finishes" because the differential equation d(subset)/dt = -T*(subset/pool) preserves ratios
  • The hypergeometric distribution is the correct statistical model for "drawing without replacement from a mixed pool"
  • For very small sub-groups (< 5 items), the hypergeometric model produces high variance — this is correct and reflects genuine uncertainty
  • Consider capping scope_rate at min(scope_rate, throughput * 0.5) if using it, to prevent divergent simulations

评价

还没有评价。欢迎分享你的使用感受。

评论

无需登录即可发表。欢迎分享使用感受、提问,或说明在哪些环境下无法运行。

还没有评论。来写第一条吧。

提交后会立即公开。请勿填写邮箱、电话等个人信息。URL 最多 2 个。

0 / 1000 字

此表单受 reCAPTCHA 保护,适用 Google 的隐私权政策和服务条款。

同一仓库的技能

Fix ArgoCD ExternalSecret deployment failing with "namespace X is not permitted in project Y". Use when: (1) ExternalSecret shows OutOfSync in ArgoCD but won't sync, (2) ArgoCD application status shows "namespace X is not permitted in project 'infrastructure'", (3) ExternalSecret targets a namespace managed by a different ArgoCD project, (4) Using apps-of-apps pattern with separate infrastructure and application projects.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

Art direction for any content — reads text, PDF, Word, HTML, PPT, then proposes 2-3 creative directions with photography style, mood, and visual language. After selection, generates AI image prompts and visual briefs section-by-section. Use when the user shares content and needs visual direction, image sourcing, or creative direction for any material.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

Fix "Null check operator used on a null value" errors when an object is set to null during an async await. Use when: (1) Object reference is nullified while awaiting, (2) Code accesses object with ! after await returns, (3) Cancel/dispose operations run concurrently with async operations on same object. Solution: capture local reference before await.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

Add custom metadata headers (x-amz-meta-*) to AWS v4 signed requests for GCS S3-compatible API. Use when: (1) Adding custom metadata to GCS uploads via S3 API, (2) Getting signature mismatch errors after adding new headers, (3) x-amz-meta-* headers being ignored or causing 403 errors. Custom headers MUST be included in canonical headers and signed headers list.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

Fix password/secret authentication failures caused by trailing newlines when creating Google Cloud secrets (or similar) with bash here-strings. Use when: (1) Password authentication fails with correct password, (2) Secret created with `<<< "value"` syntax, (3) Error like "password authentication failed" or "invalid token" despite correct value. Bash here-strings (`<<<`) add a trailing newline that corrupts secrets.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

Fix silent video/media processing failures caused by URL extraction code that filters on file extensions (.mp4, .webm, .webp). Use when: (1) Media moderation, transcoding, or analysis silently skips files from Blossom or content-addressed storage servers, (2) URL extraction from Nostr event tags (imeta, r tags) drops URLs without recognized extensions, (3) CDN fallback URLs append .mp4 but the actual server uses extensionless content-addressed paths like /{sha256}. Common in Nostr video events (kind 34236) where different clients use different URL formats.

中文简介正在准备中。当前显示原文说明。

divinevideo/divine-mobile2652026年10月23日 更新

查看 divinevideo 的全部技能

报告此技能的问题