对比 Linear 当前任务与上一份状态报告,起草项目进展更新,说明新增工作、进度、交付风险及一项待决事项;经用户批准后再发布到项目中。
Draft a Linear project status update from what actually moved — progress, risks, and the one decision that needs making. Use when someone asks for a project update, a status post, where a project stands, whether it will land on time, or what to tell stakeholders.
实测评分 未实测
查看安装方法读取 Linear 项目任务和上一份状态报告,根据两次报告之间的变化起草更新。检查已完成的任务、新增工作和目标日期的变动,并结合剩余工作量与剩余时间,判断项目进展正常、存在风险或已经偏离计划。风险会写成具体可能发生的事件及其影响,并指出相关人员需要作出的一项决定或提供的一项协助。
当您需要向不会逐条查看任务的相关人员说明项目进展和交付预期时,可以使用此技能。它也适合分享项目中途新增的工作,或提出附有负责人和期限的决策请求。报告会把变化整理成简短内容,不只依赖完成比例。
需要连接 Linear 的 MCP 工具。技能会先完整展示报告草稿,只有在您批准后才发布到项目中;如果您只要求草稿,则不会发布。报告会与上一份状态更新进行比较,因此重点是说明变化,而不是单独概括当前状况。
本介绍由 AI(OpenAI Codex)根据公开的 SKILL.md 撰写。准确的规格请查看下方原文。
AI 根据 SKILL.md 的内容检查了需要注意的操作和使用前提。评分只依据实际运行的结果(实测对比)。
不计入评分。 由 AI(OpenAI Codex)于 2026年10月29日 评估。仅供参考,安装前请同时查看原文。
安装前可以查看交给 AI 代理的指令内容。
A status update is read by people who will not open a single issue. It has to survive being the only thing they read: is this landing, what changed, and what do you need from them.
Percent-complete is the number people reach for and the one that lies. A project can sit at 70% for a month while the last three issues get harder. What tells the story is what moved since the previous update: issues completed, issues added, and target dates that shifted.
Fetch the project's issues plus its previous status update. Without the previous one you are writing a summary, not an update, and the reader cannot tell what is new.
Pick one and commit to it. Hedging every sentence is how a project stays green until the week it ships late.
| Call | What justifies it |
|---|---|
| On track | Remaining scope fits the remaining time at the current rate |
| At risk | A dependency, an unknown, or a rate that has to improve to land |
| Off track | The date will move, or scope has to be cut — say which |
If you cannot tell, the answer is at risk, and the reason is that nobody can tell.
"Backend integration is risky" gives the reader nothing. "The export endpoint is not built, we cannot finish import until it is, and the owner is on the payments migration until the 14th" tells them what to move. A risk is a specific event with a specific consequence and usually a specific person who can prevent it.
Include scope that was added mid-project. Silently absorbed scope is why the date moves, and it is invisible unless the update names it.
Most updates end with nothing to do, so nothing is done. If a decision, a person, or a descope would help, state it as the last line with a name and a date attached. One ask is better than three, because three get triaged and one gets answered.
Print the draft in full and stop. This skill drafts; publishing is the user's call. A status update is read by stakeholders and enters the project's permanent history, and a wrong trajectory or a risk named for the wrong person is not something a follow-up correction undoes — so an unreviewed post is worse than a late one.
Once they approve it, write it on the project so it lives next to the work rather than in a chat message that is gone by the next morning. Keep it to a few short paragraphs: trajectory, what moved, risks, the ask. If they asked only for a draft, stop after printing it.
还没有评价。欢迎分享你的使用感受。
无需登录即可发表。欢迎分享使用感受、提问,或说明在哪些环境下无法运行。
还没有评论。来写第一条吧。
检查 Superset 的使用情况,找出适合当前工作方式但尚未使用的功能,给出建议并介绍选项;用户选定后,可协助设置定时运行、并行工作区或共享任务等功能。
把重复任务配置为 Superset 自动化,整理智能体指令、定时或事件触发条件及运行工作区。经明确确认后创建设置,检查已保存的条件,并查看首次运行结果以调整指令。
通过 Superset 工作区的浏览器查看网页、点击、输入并检查截图或控制台信息,可用于预览运行中的网页应用、检查界面操作和表单流程。
依据 Stripe 官方文档和 API 参数定义实现支付、订阅、发票及 Webhook 集成,涵盖产品选择、沙盒测试和事件处理,并通过 Webhook 判断支付与订阅状态。
通过 Chrome DevTools Protocol 操作正在运行的 Electron 桌面应用,复现界面问题并验证修改。按实际操作流程检查页面跳转,记录截图,并对照路由、滚动位置、焦点元素和保存状态等信息。
分析 GitHub Actions 失败日志,定位最早的有效错误,区分代码缺陷、环境问题、间歇性失败和原有故障,并对照基准分支说明失败与 PR 的关系及后续处理建议。