dr-drill-runner

The full DR-drill discipline for one service: author the runbook (per-tier RTO + RPO), pre-drill checklist (data sync state, alert silencing, customer comms), drill workflow (announce, fail-over, verify, fail-back) with timestamps, the supervised run protocol (refuse without declared RTO/RPO or against production, RTO/RPO monitoring cadence, abort-on-breach), and an auditor-ready post-drill report. Backup-integrity verification (SHA-256 + signature, restore spot checks, cross-region replication, retention, key recovery) and restore-time / RTO measurement (TTF segments, PITR latency, parallel-restore tuning, trend tracking) are worked in references. Per Google Cloud DR planning guide; covers cold / warm / hot standby tier-specific patterns. Use when a scheduled or post-incident failover drill for one service is being planned, executed, or written up, or when a new tier-1 service ships without a drill defined.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qaスター 13(GitHub 13 + cccskills 0)
連携ツールAWSGoogle Cloud

実行スコア 未検証

インストール方法を見る

含まれるファイル(4)

  • SKILL.md10.7 KB
  • .tessl-plugin/plugin.json1.0 KB
  • references/backup-verification.md7.5 KB
  • references/restore-time.md9.0 KB

SKILL.md(原文)

インストールする前に、エージェントに与えられる指示の中身を確認できます。

dr-drill-runner

Per the Google Cloud DR planning guide, DR planning requires "end-to-end recovery design addressing backup, restoration, and cleanup procedures." Drills test that the procedure works AND that the team can run it. Both surface different failures.

When to use

  • Quarterly DR drill (mandatory in compliance-heavy industries: banking, healthcare, defense).
  • After a region-failover incident: rerun the drill with the lessons learned.
  • New service onboarding: every new tier-1 service ships with its drill defined.

Step 1 - Define RTO + RPO per service tier

Per the Google Cloud DR planning guide:

MetricDefinition
RTOMaximum acceptable length of time the application can be offline
RPOMaximum acceptable data loss (time window)
TierExample RTOExample RPOPattern
1 (revenue-critical)< 15 min< 1 minHot standby (active-active)
2 (customer-impacting)< 4 hr< 1 hrWarm standby
3 (internal)< 24 hr< 24 hrCold (rebuild from backup)

Document per service in a service catalog; drills enforce the contract.

Step 2 - DR-pattern tier per service

Per the Google Cloud DR planning guide:

  • Cold: Minimal preparation; recovery requires external intervention and extended downtime.
  • Warm: Basic readiness with resources available; recovery stops normal ops temporarily.
  • Hot: Continuous operation with built-in redundancy; minimal interruption.

Drill expectations differ:

  • Cold: Test bring-up from backup (restore-time tests - references/restore-time.md).
  • Warm: Test failover automation + warm-up time.
  • Hot: Test traffic redirection + sticky-session impact.

Step 3 - Pre-drill checklist

## Pre-Drill Checklist - `<service>` `<date>`

- [ ] Drill window scheduled (low-traffic; aligned with
      customer-comm window)
- [ ] Drill scope decided (region, single service, full app)
- [ ] Replication lag confirmed within RPO at T-30 min
- [ ] Monitoring alerts SILENCED for expected failure indicators
      (alert routing redirected to drill channel)
- [ ] On-call notified (avoid duplicate paging during drill)
- [ ] Customer comms sent if customer-impacting drill
- [ ] Rollback path documented (what triggers abort?)
- [ ] Drill commander assigned (owns go/no-go calls)
- [ ] Postmortem time scheduled (within 48hr of drill end)

Skipping the pre-drill = drills become incidents.

Step 4 - Drill workflow

## Drill Workflow

### T-0: Announce
- Post in #drill-channel; confirm all participants ready.
- Drill commander gives "GO" - record T-0 timestamp.

### T+0..N: Fail-over
- Execute the runbook step-by-step (everyone follows the doc; no
  improvisation).
- Capture timestamp of each step.

### Verify
- Run the verification suite (smoke + customer-impact + data integrity).
- Compare actual vs expected RTO; if RTO breached, decide:
  abort + rollback, or continue + capture learning.

### Fail-back
- If hot/warm: redirect traffic back to primary.
- If cold: tear down DR environment + restore primary.
- Verify primary is healthy before claiming drill complete.

### Cleanup
- Re-enable alerts (Step 3).
- Send "all clear" customer comms.
- Reconcile any drill-introduced data divergence.

Step 5 - Post-drill report

## Drill Report - `<service>` `<date>`

**Drill objective:** Verify warm standby fails over within RTO 4hr.

**Timeline:**
- T-30 min: Replication lag verified (52s - within RPO 1hr) ✓
- T-0: Announced, on-call silenced
- T+12m: Failover initiated
- T+47m: Standby took traffic
- T+1h22m: Verified service healthy on standby
- T+2h11m: Failback to primary
- T+3h05m: Drill complete

**RTO observed:** 1h22m (target: 4hr) ✓

**Issues found:**
1. CRITICAL: DNS TTL was 24hr in standby DNS records; users
   couldn't reach service for 23min after failover. Fix: lower
   TTL to 60s in standby zone before next drill.
2. MAJOR: Secret-manager copy step was undocumented; commander
   improvised. Fix: add Step 3.4 to runbook.
3. MINOR: One alert wasn't silenced in advance; on-call was paged.

**Action items (with owners + dates):**
- DNS TTL fix → @platform-team - 2026-05-20
- Runbook Step 3.4 → @sre - 2026-05-13
- Alert routing audit → @sre - 2026-05-13

**Next drill:** 2026-08-06 (quarterly cadence).

Step 6 - Cold-tier-specific drill pattern

Cold drills = bring up from backup. Verifies:

Step 7 - Hot-tier-specific drill pattern

Hot drills = redirect traffic between active replicas. Verifies:

  • Health check propagation (load balancer detects standby is healthy).
  • Sticky-session handling (do connections drain or break?).
  • Cache warmup not required (or warmup time is within RTO).
  • Cross-region replication lag stays within RPO during the drill.

Step 8 - Cadence

TierCadence
1Monthly (game-day style)
2Quarterly
3Annually

Per the Google Cloud DR planning guide: "test it regularly, noting any issues." Without cadence, runbooks rot.

Run protocol (executing the drill end to end)

Nobody delegates failover execution; a human drill commander runs the five stages below against this protocol. This is the rehearsed DR path - for injecting unrehearsed failures see the chaos-drill-protocol skill in this plugin.

Refuse to start when:

  • No declared RTO + RPO. Per the Google Cloud DR planning guide, RTO is "the maximum acceptable length of time that your application can be offline" and RPO bounds acceptable data loss - without them there is no pass/fail criterion.
  • The DR environment identifier matches prod / production.
  • Any CRITICAL pre-drill item fails (backup integrity, key recovery, alert silencing) - halt and emit the blocking checklist instead of proceeding.

Stage 1 - pre-drill. Run the Step 3 checklist. Verify backup SHA-256 integrity, replication lag within RPO at T-30 min, and encryption-key recoverability in the DR region per references/backup-verification.md. Verify DR-environment configuration drift is within bounds - per the AWS DR testing whitepaper, "Manage configuration drift at the DR Region. Ensure that your infrastructure, data, and configuration are as needed at the DR Region."

Stage 2 - failover. Record T-0; execute the Step 4 runbook step by step, capturing a timestamp per step. Per the AWS DR testing whitepaper, "Our experience has shown that the only error recovery that works is the path you test frequently" - a runbook step that requires improvisation is logged as a MAJOR finding immediately, never silently adapted.

Stage 3 - RTO/RPO monitor. While failover is active, sample on a fixed interval (60 s is a workable default): replication lag at the DR side, smoke-suite pass rate, and data-row spot checks. Measure time-to-functional for the Restore + Verification segments per references/restore-time.md and compare against the per-segment RTO budget. If observed TTF exceeds the RTO - abort the failover, record the breach metrics, and skip directly to the report. Record the peak RPO gap (replication lag at fail-over time); flag if it exceeds the declared RPO.

Stage 4 - fail-back. Per Step 4: redirect traffic back (warm/hot) or tear down + restore primary (cold), re-enable silenced alerts, send the all clear, verify primary health before recording fail-back complete, reconcile drill-introduced data divergence.

Stage 5 - report. Emit the Step 5 post-drill report, including the observed TTF, total RTO, and peak RPO gap versus their declared targets. Schedule the postmortem within 48 hours; every finding gets an owner + due date before the drill closes.

Anti-patterns

Anti-patternWhy it failsFix
Skip pre-drill checklistDrill becomes incidentStep 3 mandatory
One person knows the runbookBus-factor 1; drill panics when they're outRotate drill commander
Skip post-drill reportLessons lost; same issues recurStep 5 mandatory + 48hr deadline
Test failover only; skip failbackFailback is the actual prod path; bugs hideStep 4 covers both
Lower RTO target after a missed drillGoalpost movingHold the line + invest in fixes

Limitations

  • DR drills don't replace chaos engineering (this plugin's chaos skills) - they test rehearsed paths; chaos tests unrehearsed ones.
  • Cloud-managed services may have built-in regional failover that bypasses your runbook; document boundaries.
  • Some compliance regimes (FFIEC for banks) prescribe specific drill frequencies + scopes - verify per regulation.

References

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

コメント

ログインなしで書き込めます。使ってみた感想、質問、動かなかった環境などを気軽にどうぞ。

まだコメントはありません。最初のコメントを書いてみませんか。

送信するとすぐに公開されます。メールアドレスや電話番号などの個人情報は書かないでください。URL は 2 つまでです。

0 / 1000 文字

このフォームは reCAPTCHA で保護されており、Google のプライバシーポリシーと利用規約が適用されます。

同じリポジトリのスキル

Builds a CI gate that fails the build on **new** WCAG / a11y violations introduced by a PR while grandfathering pre-existing violations on a per-rule / per-page baseline. Aggregates verdicts from axe-core / pa11y / Lighthouse a11y / WAVE / IBM Equal Access scans. Use when a project has accumulated a11y debt and a strict "zero violations" gate would block every PR - the ratchet pattern lets the team ship while preventing regressions.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Workflow skill that builds an A/B-test validity checklist from an experiment proposal, walking the canonical design-correctness gates - pre-registered OEC/power/guardrails, randomization unit + SRM check, assignment integrity, telemetry, peeking discipline, novelty/primacy, post-experiment SRM re-check - into a per-experiment checklist + sign-off form. Use when launching, auditing, or governing an experiment. For pitfall mechanics (guardrails, peeking) see experiment-results-interpreter's references; to read an already-valid result use experiment-results-interpreter; for per-SDK harness tests use experiment-sdk-testing - this gates DESIGN, not SDK code.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

The single install-flow skill: the reference contract for the PWA install flow (installability gate fields, `beforeinstallprompt` handshake, per-platform paths - Android WebAPK / iOS Share menu / Firefox no-op - and the `display-mode` post-install signal, in references/install-flow-reference.md) plus the build-an-X workflow that emits the Add-to-Home-Screen suite. Walks the four-stage timeline, emitting one test per gate cell per [web.dev/articles/install-criteria][install-criteria], the deferred-prompt → `prompt()` → `userChoice` chain per [web.dev/articles/customize-install][customize-install], the iOS Safari manual-metadata branch (`apple-touch-icon`) per [web.dev/learn/pwa/installation][learn-pwa], and the post-install `(display-mode: standalone)` MQ assertion. Output: a Playwright spec with per-stage cells plus a coverage matrix. Use when a PWA's manifest, icons, or install handler change, when install conversion drops at an unknown stage, or when triaging a flaky install assertion.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Build-an-X workflow that uses an LLM to map existing tests to spec sections - given a spec doc + the test suite, the LLM identifies which tests cover which sections, surfaces uncovered sections (gap), and recommends specific tests to add. Output is a coverage matrix per spec ID. Scope is mapping tests that already exist and naming the gaps, not authoring tests for new acceptance criteria. Use when a spec doc and a test suite both exist but nobody can say which requirements are actually covered - before a release sign-off, an audit, or a decision about where to spend the next round of test effort.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Generates tests from natural-language specs (acceptance criteria, user stories, requirements) using an LLM, with confidence scoring per test case (LLM self-assessment plus heuristics: assertion quality, naming, completeness), batching uncertain cases for human review, and integration with the team's existing test framework. Use when the user asks to generate unit tests from acceptance criteria, convert user stories to test cases, automate test creation from requirements, or augment a spec-driven test suite with AI-generated stubs that are then curated before merge.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Configures Allure Report (test-runner adapter install, `allure-results` directory wiring, `categories.json` for failure classification, `history-trend.json` retention via the copy-history-between-runs pattern), runs the Allure CLI to convert `allure-results` to a static HTML site, and uploads the report as a CI artifact. Use when the team needs richer test reporting than JUnit XML - step-level attachments, per-test history, retry tracking, and severity / epic / feature labeling across framework-agnostic adapters (pytest, Jest, JUnit, TestNG, NUnit, Mocha). As a rich static HTML report generator, it is the open-source alternative to the sunset ExtentReports (JVM/.NET per-test HTML narrative); for hosted cross-run flakiness analytics rather than a static per-run report use currents-integration.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

testland のスキルをすべて見る

このスキルの問題を報告する