test-strategy-author

Authors a test strategy document (a master test plan) for a project, release, or feature - covers scope, in/out, test types per layer (unit / integration / contract / E2E / perf / security / a11y), risk-based test prioritization that maps top risks to test investment (per `risk-matrix`), tooling stack, environments, exit criteria, and ownership. Includes a risk-based test-planning workflow that turns a feature scope plus the risk matrix into a budgeted per-risk test plan with owners, effort estimates, and an explicit risks-not-addressed section. Use when a team needs the release-readiness artifact stakeholders sign off on before significant test investment, or a risk-prioritized test plan for a feature or quarter.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qaスター 13(GitHub 13 + cccskills 0)

実行スコア 未検証

インストール方法を見る

含まれるファイル(12)

  • SKILL.md11.9 KB
  • .tessl-plugin/plugin.json861 B
  • evals/admin-console-handed-the-flagship-template/criteria.json7.0 KB
  • evals/admin-console-handed-the-flagship-template/task.md12.5 KB
  • evals/monolith-split-and-a-one-line-contract-bullet/criteria.json7.9 KB
  • evals/monolith-split-and-a-one-line-contract-bullet/task.md14.4 KB
  • evals/payments-plan-with-the-budget-halved-on-monday/criteria.json8.4 KB
  • evals/payments-plan-with-the-budget-halved-on-monday/task.md11.0 KB
  • evals/replay-outage-and-a-doc-nobody-opened-in-a-year/criteria.json6.7 KB
  • evals/replay-outage-and-a-doc-nobody-opened-in-a-year/task.md9.8 KB
  • evals/stakeholder-review-thursday-with-no-matrix/criteria.json6.4 KB
  • evals/stakeholder-review-thursday-with-no-matrix/task.md8.7 KB

SKILL.md(原文)

インストールする前に、エージェントに与えられる指示の中身を確認できます。

test-strategy-author

Overview

A test strategy document answers the question "how do we know we're testing the right things?" Without it, test investment is gut-feel; with it, the team has a defensible artifact tying test work to risk and business goals.

This skill produces the document.

When to use

  • A new product / large feature is in planning; the team needs to scope test investment.
  • A multi-quarter initiative needs a published strategy stakeholders can review.
  • An audit / compliance review requires a documented strategy.
  • A new team forming around a product needs onboarding context.

For per-feature test plans (smaller scope), use the lighter-weight risk-matrix - strategy is for larger horizons.

Step 1 - Document structure

# Test Strategy - `<product / release>`

**Author:** _______________   **Date:** YYYY-MM-DD
**Status:** Draft | Review | Approved
**Stakeholders:** Engineering, Product, QA, Compliance

## 1. Scope

### In scope
- (List of features / surfaces this strategy covers)

### Out of scope
- (Explicit list of what's NOT covered, with rationale)

### Assumptions
- (List of context the strategy depends on)

## 2. Risk basis

(Reference the risk matrix per `risk-matrix`)

| Risk class | Top risks (from matrix) | Test investment |
|------------|-------------------------|-----------------|
| Business    | Promo math, Tax calculations | Property-based + UAT |
| Technical   | Webhook reliability, DB migrations | Chaos + integration |
| Regulatory  | EU GDPR, CCPA          | UAT + privacy review |
| Performance | Checkout latency        | Load + canary       |

## 3. Test types per layer (the pyramid)

Per the test pyramid (`test-pyramid-balancer`):

| Layer       | Coverage target | Tools | Owner |
|-------------|----------------:|-------|-------|
| Unit         |       80%       | Jest, pytest, JUnit | Devs |
| Integration  |       60%       | Testcontainers, supertest | Devs |
| Contract     |       100% of consumer-provider pairs | Pact | Devs |
| E2E          |       Critical paths (5-10 flows) | Playwright | QA |
| Performance  |       Critical endpoints | k6 + Lighthouse CI | QA + SRE |
| Security     |       OWASP Top 10 | Schemathesis + manual pen test | Security |
| A11y         |       WCAG 2.2 AA | axe + manual review | QA |

## 4. Tooling

(Stack inventory per layer; references to specific skills)

## 5. Environments

- **Local dev** - per-engineer; Testcontainers backing services.
- **Staging** - shared; smoke + UAT.
- **Canary** - 5% prod traffic; 30-min observation per
  prod-canary-validator.
- **Prod** - synthetic monitors per
  synthetic-monitor-author.

## 6. Test data

- **Synthetic accounts** - per synthetic-data-toolkit.
- **PII handling** - per synthetic-pii-generator.
- **Database state** - per database snapshot / restore.

## 7. Exit criteria

Release ships when:

- All AC for in-scope features pass.
- All unit/integration tests green; no flake in last 3 main runs.
- E2E critical-path suite green.
- Coverage targets met per Section 3.
- Performance targets met (p95 within budget).
- A11y regression scan green.
- Threat model reviewed for security-touching changes.
- Risk matrix Critical (>=15) all mitigated.

## 8. Ownership

| Activity              | Owner | Backup |
|-----------------------|-------|--------|
| Unit test reviews      | Devs  | Tech lead |
| E2E suite maintenance  | QA    | Dev TPM |
| Perf budget approval   | SRE   | QA |
| Threat model authorship | Security | Dev TPM |
| Synthetic monitors     | SRE   | QA |
| Risk matrix updates    | QA    | Product |

## 9. Cadence

- **Per-PR:** Lint, unit, integration, smoke E2E, coverage delta.
- **Per-merge to main:** Full E2E, perf gate.
- **Nightly:** Full regression, mutation testing weekly.
- **Pre-release:** Manual UAT sign-off, full security scan,
  release-readiness check.

## 10. Risk register snapshot

(Top 10 risks from the matrix as of strategy authoring date)

## 11. Open questions / decisions needed

- (List of unresolved items requiring stakeholder input)

## Approval

- [ ] Engineering manager
- [ ] QA lead
- [ ] Product manager
- [ ] Security (if applicable)

Step 1a - Validate the draft before approval

Before circulating for sign-off, verify the draft against its own exit gate:

  • Assert every in-scope feature in Section 1 maps to a risk class in Section 2, a layer + coverage target in Section 3, and at least one exit criterion in Section 7.
  • Assert every Section 7 exit criterion is measurable (a number or a green/red check), not a subjective phrase.

If a section cannot be filled - for example the risk matrix in Section 2 does not exist yet - record it as an open question in Section 11 rather than leaving the section blank, resolve it, then re-run this check. Collect the Approval sign-offs only once no Section 11 item still blocks release.

Step 2 - Tailor per project size

Project sizeStrategy lengthScope
Small (1-3 mo)2-3 pagesSections 1-3 + 7
Medium (1-2 quarters)5-7 pagesAll sections
Large (multi-quarter)10+ pagesAll + sub-strategies per major feature

Step 3 - Review cadence

TriggerAction
QuarterlyRe-review; update sections 2 (risks), 7 (exit), 10 (snapshot).
Major architectural changeRe-author Sections 3 + 6.
Post-incidentUpdate Section 2 (new risks); Section 7 (new exit criterion).
New compliance requirementSection 1 + Section 7.

Step 4 - Reference patterns

Common strategy patterns by product type:

Product typeStrategy emphasis
E-commerceBusiness risks (promo math, currency, tax); UAT-heavy.
SaaS B2BSecurity + multi-tenancy; contract testing critical.
Mobile nativePer-platform matrix; manual tier; performance.
Internal toolingLight strategy; integration over E2E.
Regulated (fintech, health)Heavyweight RBT (FMEA); auditable trail.

Step 5 - Risk-based test planning (per feature / per quarter)

The strategy sets the frame; a per-feature plan allocates the hours. Given a feature scope, the current risk matrix (per risk-matrix), an engineer-week budget, and the team's tooling inventory, produce a risk-prioritized test plan:

  1. Identify scope-relevant risks. Direct hits (the feature modifies code in a risk's source paths) plus area-level hits (same product area as an existing risk row). No matrix, no plan - author the matrix first.
  2. Map each risk to test types per risk-matrix Step 4 (business logic -> unit + property-based + UAT; technical -> integration + chaos + load; regulatory -> stakeholder UAT + compliance review; and so on).
  3. Estimate effort per test type (rough starting points the team calibrates): unit 0.5h, property-based 2h, integration / contract 4h, E2E 8h, manual / UAT 4h per scenario, visual regression 2h per baseline, load 1d, chaos 2d, threat model 1d.
  4. Emit the plan with a per-risk table (risk, score, class, test types, effort, owner), a budget-allocation summary with ~20% headroom for incident response and retests, and a "Risks NOT addressed (intentional)" table naming each skipped risk and why - the audit trail that distinguishes prioritization from neglect.
## Test plan - Feature `Promo banner v2`

**Risks implicated:** 6 (of 23) · **Budget:** 2 engineer-weeks · **Estimated:** 1.6 weeks (within budget)

| Risk | Score | Class | Test types | Effort | Owner |
|---|---:|---|---|---|---|
| R-1 Promo math | 15 | Business logic | + 4 unit + 1 property-based | 4 hours | Alice |
| R-2 Stripe webhook | 16 | Technical | + 1 integration + 1 chaos | 1.5 days | Bob |
| R-3 EU tax calc | 10 | Regulatory | + 1 UAT with finance | 4 hours | Carol |

### Risks NOT addressed (intentional)

| Risk | Score | Why skipped |
|---|---:|---|
| R-15 Old promo CMS migration | 3 | Below threshold; manual smoke covers. |

Planning guardrails: never plan more than 20% over budget; never skip the highest-scored Critical risk (>=15) under budget pressure - escalate to product instead; never pick test types the team has no tooling for. Version plans in markdown alongside the matrix and track revisions rather than silently rewriting prior versions.

Anti-patterns

Anti-patternWhy it failsFix
Generic strategy template not tailored to productReads like boilerplate; nobody references.Tailor per Section 1 (scope) and Section 4 (tooling).
Plan ignores the effort budgetIdealistic; team can't execute.Match plan to budget (Step 5).
Skipping Critical risks under budget pressureDefeats the prioritization purpose.Escalate to product instead (Step 5 guardrails).
No "risks NOT addressed" section in the planAudit gap; prioritization indistinguishable from neglect.Always include it (Step 5).
Strategy authored once; never reviewedBecomes obsolete; team distrusts.Quarterly cadence (Step 3).
No exit criteria"Done" is subjective; release decisions arbitrary.Section 7 - explicit + measurable.
Strategy = test planStrategy is high-level; per-feature plans are detailed (different artifact).Use risk-matrix for per-feature.
Owner column missingActivities slip; "everyone owns it = nobody."Section 8 explicit owners.
Strategy in slides, not version-controlledHistory lost; updates invisible.Markdown + git.

Limitations

  • Strategy ≠ execution. A great strategy doesn't ensure great testing - pair with per-feature plans + per-PR enforcement.
  • Quarterly cadence is a floor. Fast-moving products may need more frequent revisits.
  • Stakeholder buy-in required. A strategy nobody read is paperwork; circulate, present, get sign-off.

References

  • risk-matrix - feeds Section 2.
  • test-pyramid-balancer - feeds Section 3.
  • definition-of-done - feeds Section 7.

レビュー

まだレビューはありません。使ってみた感想をお寄せください。

コメント

ログインなしで書き込めます。使ってみた感想、質問、動かなかった環境などを気軽にどうぞ。

まだコメントはありません。最初のコメントを書いてみませんか。

送信するとすぐに公開されます。メールアドレスや電話番号などの個人情報は書かないでください。URL は 2 つまでです。

0 / 1000 文字

このフォームは reCAPTCHA で保護されており、Google のプライバシーポリシーと利用規約が適用されます。

同じリポジトリのスキル

Builds a CI gate that fails the build on **new** WCAG / a11y violations introduced by a PR while grandfathering pre-existing violations on a per-rule / per-page baseline. Aggregates verdicts from axe-core / pa11y / Lighthouse a11y / WAVE / IBM Equal Access scans. Use when a project has accumulated a11y debt and a strict "zero violations" gate would block every PR - the ratchet pattern lets the team ship while preventing regressions.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Workflow skill that builds an A/B-test validity checklist from an experiment proposal, walking the canonical design-correctness gates - pre-registered OEC/power/guardrails, randomization unit + SRM check, assignment integrity, telemetry, peeking discipline, novelty/primacy, post-experiment SRM re-check - into a per-experiment checklist + sign-off form. Use when launching, auditing, or governing an experiment. For pitfall mechanics (guardrails, peeking) see experiment-results-interpreter's references; to read an already-valid result use experiment-results-interpreter; for per-SDK harness tests use experiment-sdk-testing - this gates DESIGN, not SDK code.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

The single install-flow skill: the reference contract for the PWA install flow (installability gate fields, `beforeinstallprompt` handshake, per-platform paths - Android WebAPK / iOS Share menu / Firefox no-op - and the `display-mode` post-install signal, in references/install-flow-reference.md) plus the build-an-X workflow that emits the Add-to-Home-Screen suite. Walks the four-stage timeline, emitting one test per gate cell per [web.dev/articles/install-criteria][install-criteria], the deferred-prompt → `prompt()` → `userChoice` chain per [web.dev/articles/customize-install][customize-install], the iOS Safari manual-metadata branch (`apple-touch-icon`) per [web.dev/learn/pwa/installation][learn-pwa], and the post-install `(display-mode: standalone)` MQ assertion. Output: a Playwright spec with per-stage cells plus a coverage matrix. Use when a PWA's manifest, icons, or install handler change, when install conversion drops at an unknown stage, or when triaging a flaky install assertion.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Build-an-X workflow that uses an LLM to map existing tests to spec sections - given a spec doc + the test suite, the LLM identifies which tests cover which sections, surfaces uncovered sections (gap), and recommends specific tests to add. Output is a coverage matrix per spec ID. Scope is mapping tests that already exist and naming the gaps, not authoring tests for new acceptance criteria. Use when a spec doc and a test suite both exist but nobody can say which requirements are actually covered - before a release sign-off, an audit, or a decision about where to spend the next round of test effort.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Generates tests from natural-language specs (acceptance criteria, user stories, requirements) using an LLM, with confidence scoring per test case (LLM self-assessment plus heuristics: assertion quality, naming, completeness), batching uncertain cases for human review, and integration with the team's existing test framework. Use when the user asks to generate unit tests from acceptance criteria, convert user stories to test cases, automate test creation from requirements, or augment a spec-driven test suite with AI-generated stubs that are then curated before merge.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

Configures Allure Report (test-runner adapter install, `allure-results` directory wiring, `categories.json` for failure classification, `history-trend.json` retention via the copy-history-between-runs pattern), runs the Allure CLI to convert `allure-results` to a static HTML site, and uploads the report as a CI artifact. Use when the team needs richer test reporting than JUnit XML - step-level attachments, per-test history, retry tracking, and severity / epic / feature labeling across framework-agnostic adapters (pytest, Jest, JUnit, TestNG, NUnit, Mocha). As a rich static HTML report generator, it is the open-source alternative to the sunset ExtentReports (JVM/.NET per-test HTML narrative); for hosted cross-run flakiness analytics rather than a static per-run report use currents-integration.

日本語の概要は準備中です。原文の説明を表示しています。

testland/qa132026年10月20日 更新

testland のスキルをすべて見る

このスキルの問題を報告する