Critical Path Analyzer

Business Case

Problem Statement

Schedule management requires understanding:

  • Which activities are critical?
  • How much float exists?
  • What delays impact completion?
  • Where to focus resources?

Solution

Analyze schedule network to identify critical path, calculate float, and provide actionable schedule insights.

Technical Implementation

import pandas as pd
import numpy as np
from typing import Dict, Any, List, Optional, Set
from dataclasses import dataclass, field
from datetime import date, timedelta
from enum import Enum
from collections import defaultdict


class ActivityStatus(Enum):
    NOT_STARTED = "not_started"
    IN_PROGRESS = "in_progress"
    COMPLETED = "completed"
    DELAYED = "delayed"


@dataclass
class Activity:
    activity_id: str
    name: str
    duration: int  # days
    predecessors: List[str]
    early_start: int = 0
    early_finish: int = 0
    late_start: int = 0
    late_finish: int = 0
    total_float: int = 0
    free_float: int = 0
    is_critical: bool = False
    status: ActivityStatus = ActivityStatus.NOT_STARTED
    percent_complete: float = 0
    actual_start: Optional[date] = None
    actual_finish: Optional[date] = None


@dataclass
class CriticalPathResult:
    critical_path: List[str]
    project_duration: int
    activities: Dict[str, Activity]
    near_critical: List[str]  # Float < 5 days
    total_float_days: int


class CriticalPathAnalyzer:
    """Analyze project critical path."""

    NEAR_CRITICAL_THRESHOLD = 5  # days

    def __init__(self, project_start: date):
        self.project_start = project_start
        self.activities: Dict[str, Activity] = {}

    def add_activity(self,
                     activity_id: str,
                     name: str,
                     duration: int,
                     predecessors: List[str] = None):
        """Add activity to network."""

        self.activities[activity_id] = Activity(
            activity_id=activity_id,
            name=name,
            duration=duration,
            predecessors=predecessors or []
        )

    def import_from_dataframe(self, df: pd.DataFrame):
        """Import activities from DataFrame."""
        for _, row in df.iterrows():
            preds = row.get('predecessors', '')
            if pd.isna(preds):
                pred_list = []
            else:
                pred_list = [p.strip() for p in str(preds).split(',') if p.strip()]

            self.add_activity(
                activity_id=str(row['activity_id']),
                name=row['name'],
                duration=int(row['duration']),
                predecessors=pred_list
            )

    def _forward_pass(self):
        """Calculate early start and early finish (forward pass)."""

        # Topological sort
        sorted_activities = self._topological_sort()

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Early start = max(early finish of all predecessors)
            if not activity.predecessors:
                activity.early_start = 0
            else:
                activity.early_start = max(
                    self.activities[pred].early_finish
                    for pred in activity.predecessors
                    if pred in self.activities
                )

            activity.early_finish = activity.early_start + activity.duration

    def _backward_pass(self):
        """Calculate late start and late finish (backward pass)."""

        # Find project duration
        project_duration = max(a.early_finish for a in self.activities.values())

        # Build successors map
        successors = defaultdict(list)
        for activity_id, activity in self.activities.items():
            for pred in activity.predecessors:
                if pred in self.activities:
                    successors[pred].append(activity_id)

        # Reverse topological order
        sorted_activities = self._topological_sort()[::-1]

        for activity_id in sorted_activities:
            activity = self.activities[activity_id]

            # Late finish = min(late start of all successors)
            if activity_id not in successors or not successors[activity_id]:
                activity.late_finish = project_duration
            else:
                activity.late_finish = min(
                    self.activities[succ].late_start
                    for succ in successors[activity_id]
                )

            activity.late_start = activity.late_finish - activity.duration

            # Calculate floats
            activity.total_float = activity.late_start - activity.early_start
            activity.is_critical = activity.total_float == 0

    def _topological_sort(self) -> List[str]:
        """Topological sort of activities."""

        visited = set()
        result = []

        def visit(activity_id: str):
            if activity_id in visited:
                return
            visited.add(activity_id)

            activity = self.activities.get(activity_id)
            if activity:
                for pred in activity.predecessors:
                    if pred in self.activities:
                        visit(pred)
                result.append(activity_id)

        for activity_id in self.activities:
            visit(activity_id)

        return result

    def calculate_critical_path(self) -> CriticalPathResult:
        """Calculate critical path and all float values."""

        self._forward_pass()
        self._backward_pass()

        # Find critical path
        critical_activities = [
            a.activity_id for a in self.activities.values()
            if a.is_critical
        ]

        # Near-critical activities
        near_critical = [
            a.activity_id for a in self.activities.values()
            if 0 < a.total_float <= self.NEAR_CRITICAL_THRESHOLD
        ]

        project_duration = max(a.early_finish for a in self.activities.values())
        total_float = sum(a.total_float for a in self.activities.values())

        return CriticalPathResult(
            critical_path=critical_activities,
            project_duration=project_duration,
            activities=self.activities,
            near_critical=near_critical,
            total_float_days=total_float
        )

    def get_schedule_dates(self) -> pd.DataFrame:
        """Get schedule with dates."""

        data = []
        for activity in self.activities.values():
            early_start_date = self.project_start + timedelta(days=activity.early_start)
            early_finish_date = self.project_start + timedelta(days=activity.early_finish)
            late_start_date = self.project_start + timedelta(days=activity.late_start)
            late_finish_date = self.project_start + timedelta(days=activity.late_finish)

            data.append({
                'Activity ID': activity.activity_id,
                'Name': activity.name,
                'Duration': activity.duration,
                'Early Start': early_start_date,
                'Early Finish': early_finish_date,
                'Late Start': late_start_date,
                'Late Finish': late_finish_date,
                'Total Float': activity.total_float,
                'Critical': 'Yes' if activity.is_critical else 'No'
            })

        return pd.DataFrame(data)

    def analyze_delay_impact(self,
                             activity_id: str,
                             delay_days: int) -> Dict[str, Any]:
        """Analyze impact of delay on project."""

        activity = self.activities.get(activity_id)
        if not activity:
            return {}

        absorbed_by_float = min(delay_days, activity.total_float)
        project_delay = max(0, delay_days - activity.total_float)

        # Find affected activities
        affected = []
        if project_delay > 0:
            # Activities that could be affected (successors)
            for a in self.activities.values():
                if activity_id in a.predecessors:
                    affected.append(a.activity_id)

        return {
            'activity': activity_id,
            'delay_days': delay_days,
            'available_float': activity.total_float,
            'absorbed_by_float': absorbed_by_float,
            'project_delay': project_delay,
            'affected_activities': affected,
            'is_critical_delay': project_delay > 0
        }

    def suggest_acceleration(self,
                             target_reduction: int) -> List[Dict[str, Any]]:
        """Suggest activities to accelerate to meet target."""

        result = self.calculate_critical_path()
        suggestions = []

        # Focus on critical activities
        for activity_id in result.critical_path:
            activity = self.activities[activity_id]

            # Assume can reduce by 20% max
            max_reduction = int(activity.duration * 0.2)

            if max_reduction > 0:
                suggestions.append({
                    'activity': activity_id,
                    'name': activity.name,
                    'current_duration': activity.duration,
                    'max_reduction': max_reduction,
                    'reason': 'Critical path activity'
                })

        # Sort by potential impact
        return sorted(suggestions, key=lambda x: x['max_reduction'], reverse=True)

    def export_analysis(self, output_path: str) -> str:
        """Export analysis to Excel."""

        result = self.calculate_critical_path()

        with pd.ExcelWriter(output_path, engine='openpyxl') as writer:
            # Summary
            summary_df = pd.DataFrame([{
                'Project Start': self.project_start,
                'Project Duration': result.project_duration,
                'Project Finish': self.project_start + timedelta(days=result.project_duration),
                'Critical Activities': len(result.critical_path),
                'Near-Critical Activities': len(result.near_critical),
                'Total Float (days)': result.total_float_days
            }])
            summary_df.to_excel(writer, sheet_name='Summary', index=False)

            # Schedule
            schedule_df = self.get_schedule_dates()
            schedule_df.to_excel(writer, sheet_name='Schedule', index=False)

            # Critical Path
            critical_df = pd.DataFrame([
                {
                    'Activity': a_id,
                    'Name': self.activities[a_id].name,
                    'Duration': self.activities[a_id].duration
                }
                for a_id in result.critical_path
            ])
            critical_df.to_excel(writer, sheet_name='Critical Path', index=False)

        return output_path

Quick Start

from datetime import date

# Initialize analyzer
analyzer = CriticalPathAnalyzer(project_start=date(2024, 6, 1))

# Add activities
analyzer.add_activity("A", "Site Preparation", 10, [])
analyzer.add_activity("B", "Foundation Excavation", 15, ["A"])
analyzer.add_activity("C", "Foundation Concrete", 20, ["B"])
analyzer.add_activity("D", "Structural Steel", 30, ["C"])
analyzer.add_activity("E", "MEP Rough-in", 25, ["C"])
analyzer.add_activity("F", "Exterior Walls", 20, ["D"])
analyzer.add_activity("G", "Interior Finish", 15, ["E", "F"])

# Calculate critical path
result = analyzer.calculate_critical_path()

print(f"Project Duration: {result.project_duration} days")
print(f"Critical Path: {result.critical_path}")

Common Use Cases

1. Analyze Delay Impact

impact = analyzer.analyze_delay_impact("C", delay_days=5)
print(f"Project Delay: {impact['project_delay']} days")

2. Get Schedule Dates

schedule = analyzer.get_schedule_dates()
print(schedule[['Activity ID', 'Early Start', 'Late Finish', 'Total Float']])

3. Acceleration Suggestions

suggestions = analyzer.suggest_acceleration(target_reduction=10)
for s in suggestions:
    print(f"{s['activity']}: can reduce {s['max_reduction']} days")

Resources

  • DDC Book: Chapter 4.2 - Schedule Analysis

评价

还没有评价。欢迎分享你的使用感受。

评论

无需登录即可发表。欢迎分享使用感受、提问,或说明在哪些环境下无法运行。

还没有评论。来写第一条吧。

提交后会立即公开。请勿填写邮箱、电话等个人信息。URL 最多 2 个。

0 / 1000 字

此表单受 reCAPTCHA 保护,适用 Google 的隐私权政策和服务条款。

同一仓库的技能

Create 4D construction simulations by linking BIM elements to project schedules. Generate time-based visualizations, sequence analysis, and construction phasing with Gantt integration.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

Analyze 5000+ IFC and Revit projects at scale for patterns, benchmarks, and insights. Big data analysis for construction.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

Check construction AI systems against the EU AI Act (Regulation 2024/1689): classify risk of estimation, scheduling, CV and agent tools, document transparency, keep human oversight. Use when deploying or auditing AI in construction.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

Orchestrate multiple AI agents for construction workflows: estimator, scheduler, document, QA and safety agents coordinated by a supervisor agent, with human checkpoints. Use when automating end-to-end project processes with agentic AI.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

Create Apache Airflow DAGs for construction data pipelines. Orchestrate ETL, validation, and reporting workflows.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

Automate as-built documentation and digital handover for construction. Compile project records, generate O&M manuals, create asset databases, and ensure complete project closeout.

中文简介正在准备中。当前显示原文说明。

datadrivenconstruction/DDC_Skills_for_AI_Agents_in_Construction3682026年10月20日 更新

查看 datadrivenconstruction 的全部技能

报告此技能的问题